CCSDK R1 Amsterdam Release - M3 API Freeze Milestone
The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.
M3 Release Architecture Milestone overview is available in wiki.
Usage
Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
Fill out the Yes/No column
Provide link to evidence (when necessary)
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Architecture | Has the Project team reviewed the APIs with the Architecture Committee (ARC)? | Yes | Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough. | |
Is there a plan to address the findings the API review? | N/A | Link to plan | The plan could be as simple as a Jira issue to track the implementation of findings or a documented plan within the wiki. | |
Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval? | Yes, but need direction on specifics of TSC review and approval process | NA | In the case some changes are necessary, bring the request to the TSC for review and approval. | |
Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone? | No | If Yes, please a link to the evidence of these changes. | Critical point to understand is that change is inevitable, and that right timing and clear communication to the community will ease the process of accepting changes. | |
Provide link to the API Documentation. | ||||
Release Management | Are committed Sprint Backlog Stories been marked as "Done" in Jira board? | Yes | Provide Link to Project backlog | |
Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira? | Yes | |||
Have all findings from previous milestones been addressed? | No - still working on unit and functional test cases | Provide link to JIRA findings | ||
Development | Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar) | In Progress - some repos still under 30% | Goal: 30-50% for Incubation project | |
Is there any pending commit request older than 36 Business hours in Gerrit? | No | |||
Are all the Jenkins jobs successfully passed ( Merge-Jobs)? | Yes | Provide link to evidence | ||
Are all binaries available in Nexus? | Yes | |||
Integration and Testing | Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins? | In Progress | Provide link to evidence | |
Has the project code successfully passed the Daily Build process? | No - need to fix release version (see JIRA CCSDK-59) | Goal is to ensure the latest project commit has not broken the Integration Daily Build |