Release Process
- Self release process had a few hiccups but seems better now
- gerrit/jenkins/jira stability issues still occurring sporadicly
Product Creation
- Job Deployer for OOM (and now SO) was great CI improvement. Noticeable impact to reviewing merges when Job Deployer was offline due to lab issues.
- Addition of Azure public cloud resources is helping with the verify job load.
- Need to continue with more projects added to CI pipeline and tests targeted for the specific project (e.g., instantiateVFWCL , ./vcpe.py infra , rescustservice for SO)
Testing Process
- Adding Orange and Ericsson Labs to installation testing was a good change. More labs coming on board for this.
ONAP Project Oversight
- Jira was improvement over wiki pages for milestone tracking but it still seems onerous on the PTLs
- Need automated test result tracking for use cases
Others
- PTL meetings seem more like tracking calls. Might want to consider a PTL committee that would run the PTL meetings.
====================================================================================================================================================
Have we fixed anything captured during the Dublin Retrospective?
Release Process
- Nexus -> Dockerhub migration- Dockerhub with fat (v2) manifest support might help understand image content visibility, but what is current state of that ? PoC with Policy after 6 months ?
- Docker images optimisation - has CIA team sufficient support for this ? Different projects are doing it differently
- Need devops CI/CD to get more end2end visibility from developer perspective
- 72 hr (longevity) stability runs should be reviewed by the PTLs - monthly review in the PTL meeting
Product Creation
- OOM verify job was very helpful - finding defects before merged into the charts
- SECCOM TTL for test certificates doesn't impact the security - probably longer than a year
- AAF underestimated the difficulty of changing the service locator
- Infrastructure changes need to start very early in the release
- Plan for backward compatibility up front
- Addition of OJSI Jira has been useful to create more focus on security issues - vulnerabilities are easier to track
- Nexus vulnerabilities analysis still is very difficult - need some innovation
Testing Process
- No overall platform team - not enough people have a picture of the complete platform
- Off-line installation finding new issues - could be done earlier to find issues
- Need to do installation testing in other places than just Windriver to catch environment assumptions
- Diverse lab test envs (Orange) was helpful
- Many versions of OpenStack
- Project team engaging in the integration process accelerated the process of integration - zoom shared debug sessions (much faster than jira)
- Early start of integration testing helps issue resolution earlier than the tail end of the release
- RC0 attempt to integrate and test was not successful - no CI/CD and a large set of changes integrated at once negatively impacted system stability
ONAP Project Oversight
- POC should not intervene with the ongoing ONAP Release content/timeline i.e. Dublin. POC should not hold the following release i.e. El-Alto
- Retrospectives best done in person
- Delay in Dublin - issues not found until the very end
- Testing started earlier in the release
- Functional deployments exposed more defects and happen late in the release
- Intersystem testing should start sooner
- Instantiate vFW as a step in the CI/CD process - fully automated testing and very stable
- Requirements came too late in the process
- Need to begin the testing of Functional requirements earlier
- Teams need to be transparent into the actual status of the milestones - example: projects marked as code complete were not complete
- Delay generated by the management of the Casablanca Maintenance Release
- Lack of available lab resources
- Need to start with keystone V3 install in El Alto - installation jobs will be changed (authentication)