CCSDK/SDNC Weekly Meeting - 2021-01-27
Agenda:
ONAP project news:
LFN Developer and Test Forum scheduled next week : Feb 1, 2021 - Feb 4, 2021
No CCSDK/SDNC meeting next week due to conflict
RocketChat is being replaced by Slack (onapproject.slack.com)
Guilin Maintenance Release status:
For CCSDK/SDNC, Guilin maintenance release contains fixes for transport slicing use case:
Release builds created for CCSDK and SDNC, and helm charts have been updated.
Only remaining item is certificate refresh for cds-ui
Honolulu Release status
CCSDK and SDNC were both approved as passed M2 (Spec Freeze) milestone at special TSC meeting 1/25. Release planning templates :
Issue discovered in docker builds in master branch:
Had been using initial Honolulu release version of ccsdk/sli instead of snapshot version
Fix for this uncovered another issue with ccsdk/sli, caused by a refactoring change.
Refactoring change has been reverted for now until it can be verified in local environment
ODL Aluminum port underway:
Doing local testing to verify that docker container comes up clean before merging changes.
Next project milestone is M3 - Feature Freeze:
TSC vote scheduled for Feb 25, 2021
M3 criteria includes that all release builds must be complete and helm charts must be updated in OOM to deliver released dockers
To allow time for code reviews, release builds and OOM review, final code reviews for CCSDK and SDNC Honolulu should be submitted no later than Feb 12, 2021
Open Discussion