Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 6 Next »

Timeline (per TSC)

El Alto Weekly PlanMilestone





14-JunM0
Owner(s), List of requirements (per application, cross-applications); Project Impact (Test Only or Code Change), Dev/Test Company Engagement
21-JunM1
Content Freeze
28-Jun

DEV Sprint 1
11-Jul

Dev Sprint 1 & kick-off Test Sprint 1
18-Jul

DEV Sprint 2 - Test Sprint 1
25-Jul

DEV Sprint 2 - Test Spint 1
2-AugNo Code Freeze but RC0
Early Drop & Dev Sprint 3
9-Aug

Dev Sprint 3 - Test Sprint 2
15-AugCode FreezeEurope HolidayDev Sprint 3 - Test Sprint 2
22-Aug

Test Sprint 3
29-Aug

Test Completion/Stabilization - Branching El Alto (TBC)
5-Sep
US HolidayRelease preparation
12-SepSign-Off
Sign-Off

DCAEGEN2 (HIGHEST and HIGH) Stories - Non Security related

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

DCAEGEN2 SEC-COM Stories (HIGHEST and HIGH)

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

DCAEGEN2 Open-bug (HIGHEST and HIGH)

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

DCAEGEN2 Open-bug (MEDIUM)

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

DCAEGEN2 OJSI

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

DCAEGEN2 Stories (MEDIUM)

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

  • No labels