The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.



Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Closed" in Jira?Yes




Have all findings from previous milestones been addressed?YesN/A
DevelopmentHave all Defects of priority Highest and High been in status "Closed" in Jira?Yes



Are all JIRA issues used as a reference in a commit in status "Closed" in Jira?Yes

Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.No

Are all the Jenkins jobs successfully passed (verify + merge jobs)?Yes

Has the team delivered all their release artifacts in Nexus Release repo?

There should be at least ONE version of each artifacts available in Nexus Release repo.

Yes
Refer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?Yes

At RC2, has the Pair Wise testing table been filled out?Yes
The OOM pairwise testing has been finalized(all tests passed) on the 19th of October
At RC2, have all OOM Release Healtcheck related to your project passed?Yes

At RC2, is there a Docker image in Nexus Docker-Release repo available for each repository?Yes

Has the project code successfully passed the Daily Build process?Yes
Goal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the OOM deployment passed?YesEnsure in Jenkins External Labs all Health Check pass.

Has the Heat deployment passed?

(not a gating item for Casablanca)

YesEnsure in Jenkins External Labs all Health Check pass.
Documentation  

For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notes template?

 Yes


 For RC2, has the Documentation Team provided the final approval for your project documentation?