DRAFT PROPOSAL FOR COMMENTS
The following items are expected to be completed for the project to Pass Release Sign-Off Milestone.
Release Sign-Off Milestone overview is available in wiki.
Usage
- Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
- Fill out the Yes/No column
- Provide link to evidence (when necessary)
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Product Management | Are committed Product Backlog Stories been coded and marked as "Done" in Jira? | Link to Jira | ||
Are all tasks associated with committed Product Backlog Stories been marked as "Done" in Jira? | Link to Jira | |||
Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off | ||||
Release Management | Have all issues pertaining to FOSS been addressed? | |||
Have all findings from previous milestones been addressed? | Provide link to JIRA findings | |||
Development | Is there any pending commit request older than 24 hours in Gerrit? | |||
Are all the Jenkins jobs successfully passed (verify + merge jobs)? | ||||
Are all binaries available in Nexus? | ||||
Integration and Testing | Have all CSIT Use Cases (created by each project team) passed? | Provide link to evidence | ||
Has your project completed the end-to-end CSIT Use Case? | Provide link to evidence | |||
Is there a Docker images available for each repository? | Provide link to evidence | |||
Has the project code successfully passed the Daily Build process? | Goal is to ensure the latest project commit has not broken the Integration Daily Build | |||
Have you checked with Integration Team if your project's deliverable have successfully passed the Community Lab? | ||||
Documentation | Has your team contributed and completed work in the following 3 documentations: |