Notes:
Plan B is successful, so far
~$2k / month / 1 instance
May require additional instances to efficiently handle workload without excessive queuing
Catherine believes that we have budget. Need to follow up with Arpit.
Plan A still needs compatibility with cloud native
Probably not available until 2Q20
Session planned for DDF / Prague (Integration-Gating Retrospective)
Morgan to give presentation to TSC on status and initial results on Dec 12
David to follow up with LFIT regarding status of VEXX solution
Team decided not to have a follow-up meeting for the time being.
Meeting Notes Nov 8
Attendees:
@David McBride
@Andrew Grimberg
@Eric Debeau
@Sylvain Desbureaux
@Morgan Richomme
@DW Talton
Notes:
Sylvain says progress on Azure Plan B
Now looking at switching back to Azure Plan A.
LFIT needs additional configuration information from Orange.
Action: Sylvain to respond to RELENG-2415 on Monday
Action: DW to move status to "integration"
VEXX storage class options
SSD / HDD
From original plan, presentations to TSC on Dec 12 and Jan 23 still seems reasonable.
David to make request to Catherine/Kenny to add to agenda
Next meeting Dec 6
Meeting Notes Oct 18
Note: Follow-up was originally planned for Oct 11, but was delayed 1 week due to the unavailability of some of the key participants.
Attendees:
@David McBride
@DW Talton
@Eric Debeau
@Sylvain Desbureaux
@Morgan Richomme
@Arpit Joshipura (joined briefly and dropped)
Steve Ira (LF / joined briefly and dropped)
Notes:
No urgent issues reported.
Sylvain says that initial approach to Azure was not satisfactory. Now pursuing "Azure Plan B".
DW says that the VEXX solution is in-process. Need additional input from Orange team on storage requirements.
Sylvain to exchange mail with DW to provide additional info.
Too early to update timeline. Need to wait for additional feedback on progress in order to have sufficient visibility.
Planned follow-up meeting for Nov 8.
Meeting notes Sept 20 (Initial meeting)
Attendees:
Catherine
Sylvain
David
Arpit
Shubra
Andy
Eric
Morgan
Notes:
Agreed to pursue Azure and VEXX solutions in parallel. Community can decide on final solution at a later date.
Team (administrators of account)
@Morgan Richomme
@ChrisC
@Sylvain Desbureaux
@Sebastien Determe
@Eric Debeau
Plan/Timeline:
Create Azure account
Plan for Azure rollout (Andy's team - Sept 27)
Negotiate w Microsoft (Arpit/GB)
CI integration (community)
Team provides plan/schedule for CI integration to TSC (Morgan/Sylvain)
Followup meeting for current attendees.week of Oct 7 (David to arrange)
VEXX
Andy to follow up with Sylvain/Morgan on configuration details
Initial setup available by Oct 4 (Andy's team)
Evaluation
Team creates evaluation plan (Oct 25)
Team (above) presents initial evaluation results/cost to TSC (Dec 12 ?)
Team presents final results/cost and makes recommendation to TSC on Jan 23
Dismantle other solution