AAF R4 - RC2 Milestone Checklist



The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.





Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Product Management

Are all tasks associated with the release been marked as "Closed" in Jira?

Yes

Dublin Issues





Have all findings from previous milestones been addressed?

N/A







Development

Have all Defects of priority Highest and High been in status "Closed" in Jira?

Yes

Dublin Closed Issues



Are all JIRA issues used as a reference in a commit in status "Closed" in Jira?

Yes

Dublin Closed Issues

Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.

Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.

No



Gerrit Query: status:open label:verified -is:draft -label:Code-Review=-1 AND -label:Code-Review=-2  AND is:mergeable age:1week

Are all the Jenkins jobs successfully passed (verify + merge jobs)?

Yes

https://jenkins.onap.org/view/aaf/

https://jenkins.onap.org/view/Merge-Jobs/

Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)

No.

42.5% (up from previous 40.4% RC1)

Goal: Improvement, with Happy Path being 55% in the current release...

HOWEVER: We stated at the beginning of Dublin that we did not have enough resources to make this goal, and did best effort (assigned 1/2 of our resources)

Sonar

Guidance on Code Coverage and Static Code Analysis

Tools: Sonar



There were not enough resources or time to complete 55% for Dublin.  However, we improved by about 7.5%... 42.5%

Has the team delivered all their release artifacts in Nexus Release repo?

There should be at least ONE version of each artifacts available in Nexus Release repo.

Yes

https://nexus.onap.org/#nexus-search;quick~org.onap.aaf.authz



https://nexus.onap.org/content/repositories/releases/org/onap/aaf/authz/

Refer to Independent Versioning and Release Process for procedure

Check the certification expiry of your application. It should be valid for the next 9 months after RC0.

Yes

https://jenkins.onap.org/view/aaf/



Integration and Testing



Have all CSIT Use Cases (created by each project team) passed?



It should include at least 1 CSIT that will be run on



Lab-xxx-OOM-Daily Jenkins Job

Yes

https://jenkins.onap.org/view/CSIT/



https://jenkins.onap.org/view/aaf/



At RC2, has the Pair Wise testing table been filled out?

Yes

Integration Weather Board for Dublin Release



At RC2, have all OOM Release Healtcheck related to your project passed?

Yes

See OOM Approval Note , 5/1



At RC2, is there a Docker image in Nexus Docker-Release repo available for each repository?

Yes

Nexus project folder



Has the project code successfully passed the Daily Build process?

Yes

Jenkins project tab

Goal is to ensure the latest project commit has not broken the Integration Daily Build 

Has the OOM deployment passed?

Yes

Ensure in Jenkins External Labs all Health Check pass.



Has the project passed the Integration Sanity Tests?

Yes



Integration sanity tests in Dublin Release cover:

  • ONAP deployment

  • All components health check

  • VNF onboarding and service creation for vFW use case

  • Model distribution for vFW

  • vFW instantiation

  • vFW closed loop

  • vFW deletion

No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1

No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues

Documentation

For RC0, does the project team has solved their JIRA Documentation Tickets?

If not, what are the risks?

Yes

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/index.html

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/sections/release-notes.html

https://onap.readthedocs.io/en/latest/submodules/aaf/sms.git/docs/index.html


Doc Tickets done.



For RC1, has the team addressed all the remaining Documentation JIRA tickets ?

Yes

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/index.html

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/sections/release-notes.html

https://onap.readthedocs.io/en/latest/submodules/aaf/sms.git/docs/index.html


Doc Tickets done.



For RC1, is the project prepared for the upcoming 'Ready to review'?

Yes

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/index.html

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/sections/release-notes.html

https://onap.readthedocs.io/en/latest/submodules/aaf/sms.git/docs/index.html


Doc Tickets done.



For RC2, does the project team has solved their JIRA Documentation Tickets?

If not, what are the risks?

Yes

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/index.html

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/sections/release-notes.html

https://onap.readthedocs.io/en/latest/submodules/aaf/sms.git/docs/index.html


Doc Tickets done.