PTL 2024-04-15

We start our meetings by mentioning the project's Antitrust Policy, which you can find linked from the LF and project websites. The policy is important where multiple companies, including potential industry competitors, are participating in meetings. Please review and if you have any questions, please contact your company legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.

Agenda

START RECORDING

Duration

Agenda Item

Requested byNotes / Links
30 mins

Cross-project discussion


  • This meeting is reduced to 30 minutes
  • Rotating host

New Delhi Release Status 


LF IT Support


  • Ticket to be opened by Thomas Kulik - those repositories have no owners which blocks Documentation projects 
  • Archiving old projects at the TSC level - next TSC meeting PaweÅ‚ Pawlak 
  • Thomas and Andreas will have a meeting on April 9th.
Testing Environment


Testing Improvement



CSIT Review



ToolChain Improvement



Documentation

Other Improvement suggestion

Plan to migrate ONAP components to use RFC8040. Any update? 

----

As backup Dan is working on Biermann but not progressed. ODL is not supporting it. Restconf stack is based on RFC draft. 

  • Preferred approach is to move to RFC8040 (Alternative 1).
    • Originally proposed back in the Kohn release 
    • Plan for the New Delhi release
    • Andreas Geißler DT has someone working on the SO piece to try and port to RFC8040
    • ONAP components will be moved to RFC8040 in New Delhi
  • Alternative 2: keep maintaining Biermann interface.
    • may support either London or Montreal as a long term release
  • Alternative 3: rollback to version before Argon.
  • Alternative 4 (the most drastic): stay where we are for now and begin to work with moving off from ODL.  

As we have no solution, we can not move to ODL Potasium.

RFC changes ongoing, master to be tested this week for SO.

Andreas to prepare environment for tests, so SDNC could be updated.

Subcommittee Updates for PTLs

  1. Recommended packages upgrades are available on the restricted Wiki. Jiras are created per project. 

    Need to check NG Portal status CLM jobs. Any update?

Fiete Ostkamp to provide an update about implementation progress.
Update from Fiete Ostkamp :

Ticket opened by Fiete: https://jira.linuxfoundation.org/plugins/servlet/desk/portal/2/IT-26527

  • ongoing; Jessica and Fiete are discussing this.

We need image versions for NG Portal - work in progress by Fiete Ostkamp.

List of the ONAP components to be disabled prepared by Andreas: 

OOM New Delhi Release

Sharing Best Practices




Others



IF TIME ALLOWS ....
15 minsRelease status






5 minsUpcoming Events


10 minsRemaining Action Items



Zoom Recordings

https://zoom.us/rec/share/QH472D3zTbCRW5beJcGU5E3wjR8vR9j1J66BHLxsKZFc9yRiwzpdRdDbLs0kDhJE.I674myoiGdIgEHc4

Zoom Chat Log