DCAE R5 Testplan
Early Drop (5.0.0)
# | Sub Module | Test Cases | Status |
---|---|---|---|
1 | Deployment | Verify all platform component can be deployed and passing healthcheck | DONE |
2 | Deployment | Verify all static components identified for the release are deployed and passing healthcheck | DONE |
3 | Event Flow | Verify data flow through VES Collector | DONE |
4 | Event Flow | Verify data flow into TCA and CL o/p | DONE |
5 | Interfaces | Verify SCH interface with Inventory (through Dashboard) | DONE |
Second/Final Drop (5.0.1)
# | Sub Module | Test Cases | Status |
---|---|---|---|
1 | Deployment | Verify all platform component can be deployed and passing healthcheck | DONE |
2 | Deployment | Verify all static components identified for the release are deployed and passing healthcheck | DONE |
3 | Event Flow | Verify data flow through VES Collector | DONE |
4 | Event Flow | Verify data flow into TCA and CL o/p | DONE |
5 | Interfaces | Verify SCH interface with Inventory (through Dashboard) | TBD |