DCAE R4 RC2 Milestone Checklist

DRAFT PROPOSAL FOR COMMENTS

The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.



Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.

  2. Fill out the Yes/No column

  3. Provide link to evidence (when necessary)



Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Product Management

Are all tasks associated with the release been marked as "Closed" in Jira?

Yes

Done

Getting issues...



In-progress (pending document updates  + release tagging)

Getting issues...



Have all findings from previous milestones been addressed?

Yes

SEC-COM findings - DCAEGEN2-1365: Complete Vulnerability Review TableClosed



Development

Have all Defects of priority Highest and High been in status "Closed" in Jira?

No

New issues reported 5/29  - being investigated

Getting issues...

Provide link to JIRA issue (type bug) of priority Highest and High. 



Are all JIRA issues used as a reference in a commit in status "Closed" in Jira?

Yes



Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.

Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.

No

https://gerrit.onap.org/r/#/q/status:open+label:verified+-is:draft+-label:Code-Review%253D-1+AND+-label:Code-Review%253D-2+AND+is:mergeable+age:5days++dcaegen2

Gerrit Query: status:open label:verified -is:draft -label:Code-Review=-1 AND -label:Code-Review=-2  AND is:mergeable age:1week

Are all the Jenkins jobs successfully passed (verify + merge jobs)?

Yes

https://jenkins.onap.org/view/dcaegen2/

[ONAP Helpdesk #60449] - dcaegen2-analytics-pnda-master-merge-java  (being worked as POC - not critical for Dublin)

https://jenkins.onap.org/view/Merge-Jobs/

Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)

Yes

All DCAE components (20) coverage is > 55%.

dcaegen2/analytics/tca  → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.analytics.tca%3Adcae-analytics - 77.1%

dcaegen2/collectors/snmptrap → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.collectors%3Asnmptrap - 56.5%

dcaegen2/collectors/ves → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.collectors.ves%3AVESCollector - 68.2%

dcaegen2/platform/configbinding → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.platform%3Aconfigbinding - 79.7%

dcaegen2/platform/plugins → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.platform%3Aplugins - 55.4%

dcaegen2/platform/inventory-api → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.platform%3Ainventory-api  - 58%

dcaegen2/platform/policy-handler → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.platform%3Apolicy-handler - 73.2%

dcaegen2/platform/cli → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.platform.cli%3Acli - 72.1%

dcaegen2/utils → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.utils%3Autils - 78.4%

dcaegen2/services/heartbeat → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.platform%3Aheartbeat - 57.3%

dcaegen2/services/mapper → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.services.mapper%3Amapper - 71.9%

dcaegen2/services/prh → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.services%3Aprh - 78.7%

dcaegen2/collectors/hv-ves → 62% (kotlin)

dcaegen2/collectors/datafile → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.collectors%3Adatafile - 77.2%

dcaegen2/analytics/tca-gen2 → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.analytics.tca-gen2%3Atca-gen2-parent - 57.3%

dcaegen2/services/son-handler → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.services.son-handler%3Ason-handler -  55.3%

dcaegen2/services/pm-mapper → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.services%3Apm-mapper -  79.5%

dcaegen2/services/bbs-eventprocessor → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.services.components%3Abbs-event-processor -  74.3%

dcaegen2/services/sdk → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.services%3Asdk - 58.5%

dcaegen2/collector/restconf  → https://sonar.onap.org/dashboard?id=org.onap.dcaegen2.collectors.restconf%3Arestconfcollector - 64%



Goal: 55% for Incubation project in the current release

Sonar

Guidance on Code Coverage and Static Code Analysis

Tools: Sonar

Has the team delivered all their release artifacts in Nexus Release repo?

There should be at least ONE version of each artifacts available in Nexus Release repo.

Yes

04/30 - Some artifacts released; others requested to LF today [ONAP Helpdesk #74427] DCAE artifacts release request (Dublin) #3

Refer to Independent Versioning and Release Process for procedure

Check the certification expiry of your application. It should be valid for the next 9 months after RC0.

Yes





Integration and Testing



Have all CSIT Use Cases (created by each project team) passed?



It should include at least 1 CSIT that will be run on



Lab-xxx-OOM-Daily Jenkins Job

Yes

All the other DCAE CSIT (below) are passing

dcaegen2-pmmapper-master-csit-pmmapper

dcaegen2-collectors-hv-ves-master-csit-testsuites 

dcaegen2-services-bbs-event-processor-master-csit-bbs-testsuites

dcaegen2-master-csit-testsuites (VES)

dcaegen2-master-csit-prh-testsuites

dcaegen2-collectors-datafile-master-csit-Functional-suite

dcaegen2-collectors-datafile-master-csit-ManagementInterface-suite

HV-VES and PRH added for testsuite repo



As things are moving fast, we want to ensure CSIT are still "green".



At RC0, has the Pair Wise testing table been filled out?

Yes

Completed 5/9.



DCAE Pair Wise Testing for Dublin Release

Integration Weather Board for Dublin Release



At RC0, have all OOM Release Healtcheck related to your project passed?

Yes

As of 4/30



At RC0, is there a Docker image in Nexus Docker-Release repo available for each repository?

Yes

5/1 - This is completed; ONAP Helpdesk #74427] DCAE artifacts release request (Dublin) #3

04/30 - Some artifacts released; others requested to LF today [ONAP Helpdesk #74427] DCAE artifacts release request (Dublin) #3



Has the project code successfully passed the Daily Build process?

Yes



Goal is to ensure the latest project commit has not broken the Integration Daily Build 

Has the OOM deployment passed?

Yes

As of 4/30

Ensure in Jenkins External Labs all Health Check pass.



Has the project passed the Integration Sanity Tests?

Yes



Integration sanity tests in Dublin Release cover:

  • ONAP deployment

  • All components health check

  • VNF onboarding and service creation for vFW use case

  • Model distribution for vFW

  • vFW instantiation

  • vFW closed loop

  • vFW deletion

No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1

No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues

Documentation

For RC0, does the project team has solved their JIRA Documentation Tickets?

If not, what are the risks?

Yes



JIRA Query (Bugs Only)

project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels = Documentation OR project = Documentation) AND issuetype= Bug AND  fixversion = "Dublin Release" AND status != Closed ORDER BY issuetype DESC, fixVersion ASC, status DESC, priority DESC, updated DESC

For RC1, has the team addressed all the remaining Documentation JIRA tickets ?

Yes

Looking to close DCAE documentation updates by EOW and create release branch for documentation repo

JIRA Query

project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels=Documentation OR project=Documentation) AND status != Closed ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC

For RC1, is the project prepared for the upcoming 'Ready to review'?

Yes



Documentation related patches should be reviewed by the documentation team to make sure everyone follows style guides.

For RC2, has the team addressed all the remaining Documentation JIRA tickets identified during the review?

Yes



JIRA Query

project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels=Documentation OR project=Documentation) AND status != Closed ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC