[portal-platform] 08-29-2018 portal weekly meeting
Agenda:
M3 Due 8/23/18 finalize :
Portal-343 Sireesh will check in today or tomorrow - done
Portal-247 Sonar scan Hari - Leimeng send him an email in-progress
Portal-272 Sireesh will change status - adding more test cases:for Language, SDK, etc
Portal-316 and Portal-314 turn on Raptor Reports on VM 11 menu for SDK - Leimeng,; menu in gerrit has to be activated if it passes; Portal-314 is closed
Portal-275 check to see if postponed to Dublin - Lorraine check today
Portal- 288 code is done, documentation needs to be updated and code to be tested - Sunder ??
Portal-362 Lorraine submitted, Sunder to merge - done
Code Coverage needs to be maintained at 50% or the current coverage better than 50%. (70% on Portal, on 64% SDK) - check offline
SDK repo - Naveen is working on new SDK code coverage changes. New SDK commits made - Please add more reviewers - "Amrita Kundu" <amrkundu@in.ibm.com> and Mani are working part time on the code coverage
Prasad/Swapnali - not active on the code commits.
Please use Epic - PORTAL-268 - for code coverage - PORTAL-273; for sonar issues - PORTAL-247; (focused on Portal repo).
Design for Angular update
Source code to be committed for Angular upgrade in a separate folder under SDK (waiting on fixing the build process which is taking long) - gerrit review is done - waiting to merge.
update the xml file - Saravanan.- still reviewing, pending
Bump up the pom and docker versions to snapshots and deploy to T-Lab and Windriver (change in OOM as needed) - Saravanan/Sunder/Manoop.
fonts and icons abstraction so that they can be switched with a flag configuration - Saravanan (decided to achieve this configuration during the build rather than at runtime)
One screen implementation needs review with Sunder. - complete , will meet before checking the code
Lorraine to run grep scan for ecomp keyword - done - Review with Sunder/Manoop - will send them result in email - forward scan email to Hima and Lorraine
Look for the vm host names in the files - to clean up - Lorraine already made commit for this changes - Hima can help if requires java file changes.
ECOMP to ONAP word changes in license text - done in Code Cloud - waiting to move to Gerrit - 08/01
Need to review the MUSIC related classes to cleanup the ECOMP keywords - Hima looking into it. (changes are being committed in internal codecloud, soon will be pushed to gerrit).
Hima working through changes - still working on it , Lorraine will help
Moving the current CSIT tests to test-suites repo - may need to create a new JIRA item to track - Sireesh/Ritesh - PORTAL-343: Moving Portal CSIT tests to test-suites repoClosed
Submit the changes into test-suites and add reviewers - @Brian Freeman and @Gary Wu - ETA 08/13 - done
Reviews being done and Sireesh fixing the files. - done
Once merged, please request Gary to trigger portal scripts from External labs OOM jenkins jobs - Sireesh. - working with Gary
Runs from local, needs to be tested in Jenkins
Sireesh/Ritesh to plan the test cases for the new features planned to Casablanca - Portal R3 Casablanca Functional Test Cases
Regarding reporting feature - there is meeting scheduled for Friday. - meeting was held, some test cases are written
Regarding language feature - following up with @Tao Shen. - had a call, Tao sent document (5 APIs), GUI page needs updating Leimeng will sent email, another meeting Friday
Sireesh/Saravanan to followup with Sitharam for resources on AAF - CADI risk in Portal - Looking for response from Sitharam - meeting happened on 8/14
Two resources expected from ECOMP's team (Sireesha and Hima/Hema).
@SITHARAMAN T R to provide list of resources for this task.
@Sunder Tattavarada and @Manoop Talasila to prepare the plan and tasks for this feature and provide ETAs.
@Jonathan Gathman from AAF to provide support and guidance on all the AAF details. Had call with Jonathan, Sunder working on it, Saravanan - certificate work will be done after Sunder gives them info
met with Jonathan 70% done;
two steps 2.4 has rest implementation done; 2.5 will have CADI; email sent and partners
Jonathan having a few roadblocks, has to make some changes
Logging standards analysis done by Lorraine - link to the expected changes for logging - ONAP Application Logging Specification v1.2 (Casablanca)
Micheal O Brien reviewing the logging changes that can be done in portal/sdk - followup - PORTAL-170: Logging ImprovementClosed.
Review the current MDCs in the "EPEELFLoggerAdvice.java" class and others that might have.
Lorraine will follow up with Michael tomorrow .
Review needs to be done with Sunder, Shireesha. Kotta by Sep 1st week with Michael's changes
Some of the logging code is being refactored
Attendees: and Hima
Release Discussion Items:
Internationalization language support plan for Casablanca - PORTAL-267 - (Tao Shen shentao@chinamobile.com)
Tao is updating the API definition at appropriate documentation in wiki and rst files.
Choose language/internal components
In discussion by larger community (Use Case UI Team), expecting implementation details (Leimeng to followup)
Leimeng has sent email to Tao Shen shentao@chinamobile.com on this topic and is waitng for his return email
Testing
CSIT test for new Casablanca features - Sunder to schedule a session to go over the new features.
Convert ECOMP selenium tests into CSIT ONAP Robot Framework tests - Sunder/Sireesh - Sunder to provide the ECOMP test scripts to Sireesh.
Enable JavaScript Unit tests. (How will this impact the angular upgrade? Will these unit tests work as is even after upgrade?).
Code Coverage needs to be maintained at 50% on both portal and portal/sdk repos without JS coverage.
Reporting feature enhancement in portal/sdk - PORTAL-312: Reporting feature enhancement in portal/sdkClosed - Sundar R
Defect fixes (Hima looking into items)
Casablanca Release (Nov 2018)
M1 Release Planning Jun 28, 2018
M1 Release Planning Checklist Jun 28, 2018
M2 Functionality Freeze Jul 26, 2018
M3 API/Data Model Freeze Aug 23, 2018
M4 Code Freeze Sep 20, 2018
RC0 Checklist Oct 11, 2018
RC1 Checklist Oct 25, 2018
RC2 Checklist Nov 8, 2018
Release Delivery Nov 15, 2018