Pomba Casablanca M3 Deliverables for API Freeze Milestone Checklist Template

Pomba Casablanca M3 Deliverables for API Freeze Milestone Checklist Template

The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.

M3 Release Architecture Milestone overview is available in wiki.

Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.

  2. Fill out the Yes/No column

  3. Provide link to evidence (when necessary)

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Architecture



Has the Project team reviewed the APIs with the Architecture Committee (ARC)?

Yes

20180814

Pomba Casablanca Architecture Alignment



Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough.

Is there a plan to address the findings the API review?

Yes





The plan could be as simple as a Jira issue to track the implementation of findings or a documented plan within the wiki.

Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval?

Yes

NA

In the case some changes are necessary, bring the request to the TSC for review and approval.

Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone?

No (Some content may slip to Dublin)

If Yes, please a link to the evidence of these changes.

Critical point to understand is that change is inevitable, and that right timing and clear communication to the community will ease the process of accepting changes.

Provide link to the API Documentation.





  1. POMBA Audit Initiation Swagger

  2. POMBA Context Builder Swagger

  3. Network Discovery API Swagger

  4. POMBA DMaaP

Release Management

Are committed Sprint Backlog Stories been marked as "Done" in Jira board?

As completed

type key summary assignee reporter priority status resolution created updated due
Loading...
Refresh

Jira Query

Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira?

Yes





Have all findings from previous milestones been addressed?

N/A

Provide link to JIRA findings



Development

Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)

Yes

Goal: 50% for Incubation project in Beijing

LOG-621: POMBA: code coverage 50% targetClosed

Guidance on Code Coverage and Static Code Analysis

Tools: Sonar

Is there any pending commit request older than 36 Business hours in Gerrit?

No





Do you have a plan to address by M4 the Critical  vulnerabilities in the third party libraries used within your project?

   Yes

LOG-616: POMBA: Address CLM critical issues by M4/RC2 - 6 High across all projectsClosed

Ensure by M4 the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo.

Are all the Jenkins jobs successfully passed ( Merge-Jobs)?

Yes

Provide link to evidence



Are all binaries available in Nexus?

Yes

Provide link to evidence



Integration and Testing


Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins?

Yes

Provide link to evidence

POMBA - Functional Test Cases

LOG-212: POMBA: CSIT testingClosed



Has the project code successfully passed the Daily Build process?

Yes



Goal is to ensure the latest project commit has not broken the Integration Daily Build