AAI M3 Deliverables for API Freeze Milestone Checklist

AAI M3 Deliverables for API Freeze Milestone Checklist

The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.

M3 Release Architecture Milestone overview is available in wiki.

 

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Architecture

 

Has the Project team reviewed the APIs with the Architecture Committee (ARC)?

Yes

Review 8/22

Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough.

Is there a plan to address the findings the API review?

Yes

https://lf-onap.atlassian.net/browse/AAI-210

https://lf-onap.atlassian.net/browse/AAI-184

Need to finalize the VF-C schema changes, if any. Need to finalize attributes needs for ESR.

Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval?

Yes

NA

In the case some changes are necessary, bring the request to the TSC for review and approval.

Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone?

Yes

https://lf-onap.atlassian.net/browse/AAI-32

Introduction to A&AI Repositories

Moved AAF integration into Beijing release. We have made babel, gizmo, and champ Beijing incubation

Provide link to the API Documentation.

A&AI REST API Documentation

 

 

Release Management

Are committed Sprint Backlog Stories been marked as "Done" in Jira board?

Yes

A&AI JIRA Board

 

Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira?

Yes

 

 

Have all findings from previous milestones been addressed?

Yes

Provide link to JIRA findings

 

Development

Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)

Yes

 

Goal: 30-50% for Incubation project

Guidance on Code Coverage and Static Code Analysis

Tools: Sonar

Is there any pending commit request older than 36 Business hours in Gerrit?

No

 

 

Are all the Jenkins jobs successfully passed ( Merge-Jobs)?

Yes, every job has passed at some point.

A&AI Jenkins

The one job that has never passed is being removed as part of this commit: https://gerrit.onap.org/r/#/c/14577/2

Are all binaries available in Nexus?

Yes

Nexus A&AI

 

Integration and Testing

Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins?

Yes

https://jenkins.onap.org/view/CSIT/

 

Has the project code successfully passed the Daily Build process?

Yes

 

Goal is to ensure the latest project commit has not broken the Integration Daily Build