Color Guide

ONLY Completed items should be green. 

COMPLETED

PROGRESSING >= 90%

PROGRESSING <90%

TARGET COMPLETION

#

Use Case

Functional Requirement

Nonfunctional Requirement

Test Cases

Lab

Integration

Test Lead

RC0 Status

(remaining days of effort)

RC1

Status

RC2 Status

TSC Feedback (RC2)

Details

Doc status

CI integration*

Components involved

Comments

1

vFW

Model Driven Control Loop Design 

vFWCL

Testing with GRA_API in VID/SO/SDNC


(vDNS is part of scale out use case below #11)


Intel / Windriver

Azure

COMPLETED

(need to regression on final dockers)

COMPLETED


Waiting feedback about regression on final dockers

Distribtion

COMPLETED

Instantiation

COMPLETED

Control Loop

COMPLETED

Work around applied for appc.properties in Jira

Blocker:

INT-1568 - Getting issue details... STATUS


APPC-1876 - Getting issue details... STATUS


?

SDC

Dmaap

SDNC

SO

AAI

Policy

Appc

...


3

vCPE with TOSCA

MODELING-354 - Getting issue details... STATUS

VFC-1654 - Getting issue details... STATUS

USECASEUI-438 - Getting issue details... STATUS


vCPE(tosca) - Integration test cases

CMCC / Intel 

COMPLETED

COMPLETED




https://docs.onap.org/en/latest/submodules/integration.git/docs/docs_vCPE_with_Tosca_VNF.html

minor updates

WIP

INT-1355 - Getting issue details... STATUS


SDC

Dmaap

AAI

Multicloud

VFC

UUI

Modeling

...



45G - Realtime PM and High Volume Stream Data Collection5G - Real Time PM and High Volume Stream Data Collection - Integration Test Cases

Intel / Windriver

COMPLETED


COMPLETED





Test Cases passed on RC0

Test status:

5G - Real Time PM and High Volume Stream Data Collection - Integration Test Cases

https://onap.readthedocs.io/en/latest/submodules/integration.git/docs/docs_5g_rtpm.html#docs-realtime-pm

Yes

CSIT's

DCAE
5

5G - PNF PnP

REQ-134 - Getting issue details... STATUS

5G - PNF PnP - Integration Test Cases

Intel / Windriver

COMPLETED


COMPLETED



Test Cases passed on RC0

https://docs.onap.org/en/latest/submodules/integration.git/docs/docs_5g_pnf_pnp.html#docs-5g-pnf-pnp

minor updates

Already in CI gate

16.04:

Currently released image for SO-BPMN (1.6.0 form27'th of March) is not working.

Image from today 16.04 is sufficient and works. v2/onap/so/bpmn-infra/manifests/1.6.0-20200416T0645 
→ There will be need to release new SO images

6

 5G - Bulk PM

REQ-129 - Getting issue details... STATUS


5G - Bulk PM - Test Status

Ericsson Labjames cuddy

COMPLETED

COMPLETED

CCOMPLETEDOMPLETED




DCAEGEN2-2217 - Getting issue details... STATUS

Introduced in Gate after RC1

DCAEGEN2-2217 - Getting issue details... STATUS

8

5G - PNF Pre-Onboarding & Onboarding

SOL 004 (VNF Package Security)

REQ-135 - Getting issue details... STATUS

5G - Preonboarding/Onboarding - Test Status

Intel / Windriver

PNF Preonboarding (VNF SDK):

Marcin Przybysz

Krzysztof Kuzmicki

Dermot Melia

PNF Onboarding (SDC):

Andy Walshe

PROGRESSING >= 90%

15.05

PROGRESSING >= 90%

26.05




image 1.5.2 that has been release on 22nd of May contains all corrections waiting to have it in OOM for Frankfurt


SOL004 option 1 need to be checked manually in VNFSDK 

SDC-2981 - Getting issue details... STATUS   - blocks automated test cases for SOL004 in PNF Onboarding part

VNFSDK-582 - Getting issue details... STATUS

VNFSDK-581 - Getting issue details... STATUS



16.04:

New image has been released /onap/vnfsdk/refrepo:1.5.1 

  • package integrity rules are present (SOL004 option 1) - need to have prepared  automated test cases
  • PNF SW update validation rules are present need to have prepared  automated test cases
  • Full integration  automation of pre-onboarding and onboarding tests is ongoing
95G - OOF SON: OOF (SON) in R5 El Alto, OOF (SON) in R6 Frankfurt

Integration Test

OWL / Windriver

COMPLETED

MAY 22






Use case: https://docs.onap.org/en/dublin/submodules/integration.git/docs/docs_5G_oof_pci.html

SON-Handler MS (DCAE): https://onap.readthedocs.io/en/latest/submodules/dcaegen2.git/docs/sections/services/son-handler/index.html

Updates for Frankfurt submitted (INT-1466 and DCAEGEN2-2104)

Stretch goal, will take this up in next releaseDCAE (SON-Handler MS), Policy, SDN-C, OOF

Use case integration test cases status can be found in below page

Integration Test


10E2E Network SlicingTest StatusWindriver/CMCC

COMPLETED

MAY 22TH

updated on May 18th
COMPLETED




Test is in progress.

Use case documentation submitted (INT-1468). 

Stretch goal, will take this up in next release.

UUI, EXT-API, SO, OOF

(Test only: SDC, A&AI, Poilcy)

OPTFRA-749 - Getting issue details... STATUS

11Scale Out

Scale Out - Integration Test Cases and Status

Intel / Windriver

COMPLETED




https://onap.readthedocs.io/en/lastest/submodules/integration.git/docs/docs_scaleout.html#docs-scaleout

minor updates


APPC

VID

DCAE

SO

Policy

...

Some new platform capabilities have been developed in SO and CDS. If they can’t be used for some reason, we’ll fall back to using the current process.
12CCVPN-E LINE over OTN NNICCVPN Integration Test CasesHuawei

COMPLETED

MAY 12



COMPLETED


SDNC-1184 - Getting issue details... STATUS

We have an issue in the SDNC DG (SDNC-1184), which will be fixed by May 12th. After that, the integration test will be completed. 

https://onap.readthedocs.io/en/latest/submodules/integration.git/docs/docs_CCVPN.html#docs-ccvpn

updates will be based on  Frankfurt scope


SDNC

AAI

OOF

UUI


12.1CCVPN - MDONSMDONS Integration Test Case Fujitsu/Orange

PROGRESSING >= 90%

MAY 15TH



Did we complete the testing? If not then what's the new target date?


Test Environment:

  1. Master branch instance  in Fujitsu
  2. Windriver SB00
    1. Issue at VNF resource 'certify'  (Fixed)
    2. Expect SO 1.6.1 to be deployed where the blocking issues and.

Current  blocker: SO-2827 - Getting issue details... STATUS


https://onap.readthedocs.io/en/latest/submodules/integration.git/docs/docs_CCVPN.html#docs-ccvpn

updates will be based on  Frankfurt scope


SO - C

A&AI - C

SDN-C - C

UUI - C

SDC - TO

ExtAPI - TO


13HPA vFW/vDNS

vFW/vDNS HPA Testing

(Test Plan 1 in

HPA & Cloud Agnostic Intent - R3 Test Plan)
Intel / Windriver

COMPLETED

MAY 22

COMPLETED





One pass has been more or less completed with workarounds the following bugs:

SO-2940 - Getting issue details... STATUS

  OPTFRA-750 - Getting issue details... STATUS

OPTFRA-756 - Getting issue details... STATUS

As with line 20 below, manual workaround for the following is being used:  MSB-467 - Getting issue details... STATUS  

Other known issues:

Using patch from  CLI-269 - Getting issue details... STATUS  to manually use CLI updates for loading policies.  Not required - as curl commands can also be used.

Calling this done based on testing done with workaround/fixes for the above noted issues.

https://onap.readthedocs.io/en/elalto/submodules/integration.git/docs/docs_vfwHPA.html#docs-vfw-hpa

SO

SDC

VID

OOF

Policy

SDNC

AAI


15

Change Management Frankfurt Extensions


REQ-187 - Getting issue details... STATUS

REQ-191 - Getting issue details... STATUS

Steps:

1) Instantiation of vFWDT

2) Configuration of OOF Policies for vFWDT

3) Execution of OSDF/HAS requests for data collection

4) Configuration of VNF profiles in CDT

5) Configuration of Ansible Server

6) Execution of the workflow


Intel / Windriver

COMPLETED

Updated 12th of May

COMPLETED

Updated 14th of May




1) PASS

2) PASS/WORKAROUND

3) PASS

4) PASS

5) PASS

6) PASS

90% Completed

PASSED conditionally with a workaround for 

OPTFRA-750 - Getting issue details... STATUS


El Alto doc good: https://docs.onap.org/en/latest/submodules/integration.git/docs/docs_vFWDT.html#docs-vfw-traffic

but major updates needed (as the use cases evolved)


Major documentation change completed https://gerrit.onap.org/r/c/integration/+/102853

Minor change with policy upload change still to be updated.


Documentation update completed.


No

Use case will be semi-automated. All the steps can be performed with scripts but still CI scripts needs to be build. Planned for next release.

SDC

AAI

SO

VID

OOF

Policy

APPC

Use case will be renamed and include upgrade
16

PNF Software Upgrade

  • PNF / Enhancement on PNF Software Upgrade with EM with Ansible

Steps:

1) Execute custom PNF SW Upgrade WF from SO

2) SO send conventional LCM API to SDNC/CCSDK

3) Controller send ansible commands to AS

4) AS contact EM with ansible

Huawei

INT-1207 - Getting issue details... STATUS

COMPLETED

COMPLETED



Test results:

Test Status of Enhancement on PNF S/W Upgrade with EM with Ansible

Documentation containing new scenarios will be upadted in R6.

INT-1209 - Getting issue details... STATUS




18BBS Broadband Service Use Case (Frankfurt)BBS Integration Test Cases (Frankfurt)BBS Swisscom Lab

45% COMPLETED

MAY 25

Swisscom lab is closed

Update (May 22): running BBS integration test cases in UNH-IOL. Some issues with SO. Frankfurt OOM release installs SO version 1.6.0, but version 1.6.1 is needed

Blocker SO-2827 - Getting issue details... STATUS




Frankfurt doc: https://docs.onap.org/en/latest/submodules/integration.git/docs/docs_BBS.html 

No, planned for future releases


we need to find a solution to emulate 3rd party controllers first. Our use case relies on physical equipment and external controllers and we can only test it in the Swisscom lab at the moment. We may have a second lab with the required equipment in UNH-IOL, but it is not confirmed yet.
19VSP Compliance and Validation Check within SDC (Frankfurt) - Phase 2VSP Compliance Check within SDC - Integration Test PlanVodafone

COMPLETED




https://wiki.onap.org/display/DW/VSP+Compliance+and+Validation+Check+within+SDC+%28Frankfurt%29+-+Phase+2#VSPComplianceandValidationCheckwithinSDC(Frankfurt)Phase2-VSPComplianceCheckwithinSDC-IntegrationTestPlan

https://onap-sdc.readthedocs.io/en/latest/consumedapis.html

https://onap-doc.readthedocs.io/projects/onap-sdc/en/latest/externaltesting.html

No

SDC

VTP


20K8S based Cloud Region Support - vFW Use case

Deploy vFW Helm Chart using Multicloud K8s Plugin in Kubernetes Cloud REQ-182 - Getting issue details... STATUS

intel / Windriver

PROGRESSING >= 90%

MAY 15

COMPLETED



completed test with manual workaround for following 3 items:

Known issues:

MSB-467 - Getting issue details... STATUS  using manual workaround to get past this for now (fixes for this have been tested and verified)

MULTICLOUD-1053 - Getting issue details... STATUS  has been resolved.

SDC-2972 - Getting issue details... STATUS  using manual workaround to get past this for now. (reported to be working now)

After above are fixed, a retest can be made to verify.

Calling this done based on testing done with fixes/workarounds of known issues.





21K8S based Cloud Region Support - EdgeXFoundry Use caseDeploy EdgeXFoundry Helm Chart using Multicloud K8s Plugin in Kubernetes CloudIntel/ Windriver

PROGRESSING >= 90%

MAY 15

COMPLETED



same as line #20.



22ORAN A1 Adapter Implemented in ONAP (SDNR) A1 Adapter Test CasesIntel/Windriver

PROGRESSING >= 90%

MAY 15TH

COMPLETED



Need to re-test SSL enabled HTTPS ports among DMAAP message router, SDNC DMAAP listener and SDNC dockers

SDNC-1183 - Getting issue details... STATUS

SDNC-1138 - Getting issue details... STATUS

SDNC-1167 - Getting issue details... STATUS

OOM-2400 - Getting issue details... STATUS





23PNF Software Upgrade using direct Netconf/Yang interface with PNFPNF Software Upgrade Using direct NETCONF/YANG interfacewithPNFTestCasesIntel

INT-1308 - Getting issue details... STATUS

COMPLETED

COMPLETED

COMPLETED






24Enable PNF software version at onboardingPNF Software Information Onboarding Test CasesEricsson LabFormer user (Deleted)

INT-1307 - Getting issue details... STATUS

COMPLETED

COMPLETED

COMPLETED







25

K8s CDS Support (vFW_CDS_CNF) REQ-182 - Getting issue details... STATUS (SO and CDS Macro flow with Helm Chart)

  1. Installation of KUD k8s environment
  2. Configuration of k8s tenant in AAI
  3. Configuration of kud/k8s region in multicloud
  4. Configuration of kud/k8s region in SO
  5. Modification of SO BPMN configuration
  6. Onboarding of artifacts to SDC
  7. Design and distribution of service in SDC
  8. Instantiation of Service with SO
Private lab + Intel/Windriver community lab

INT-1184 - Getting issue details... STATUS PROGRESSING >= 90%

MAY 15TH

Updated 07.05

COMPLETED
With workarounds for
MSB-467 - Getting issue details... STATUS

Updated 14.05



Currently successfully verified with workarounds.

Raw recording of live verification session in Windriver lab

BLOCKERS:

MSB-467 - Getting issue details... STATUS

Fix under this last ticket is currently under verification

https://docs.onap.org/en/latest/submodules/integration.git/docs/docs_vFW_CNF_CDS.html but needs to be updated according to latest verification statusAutomation of usecase targeted for G release

07.05: Currently usecase has been verified to work both in internal and windriver lab with workaround. Ongoing tests regarding verifying fixes provided under blocker jiras.

08.05: Removed blocker jiras that were tested for being corrected.

14.05: Updating fix brought under MSB-467 to fully cover issue, as previous patch was found incomplete

26

ETSI Alignment

SO plugin to support SOL003 to connect to an external VNFM and ETSI package management

  1. SDC users onboards SOL004 VNF package to SDC
  2. SDC users distributes SOL004 VNF package to ONAP SO
  3. SO receives the SOL004 VNF packages from SDC
  4. ONAP SO triggers ETSI Catalog Manager to store the original vendor SOL004 VNF package
  5. ETSI Catalog Manager gets the SOL004 VNF package from SDC and stores it to its database
  6. ETSI Catalog Manager sends a package notification to SOL003 Adapter
  7. SOL004 Adapter forwards the notification to SVNFM (Simulator)
  8. SVNFM queries SOL003 Adapter for the SOL004 VNF package
  9. SOL003 Adapter queries ETSI Catalog Manager for the SOL004 VNF package 
  10. ETSI Catalog Manager returns the SOL004 VNF package to the SOL003 Adapter 
  11. SOL003 Adapter returns the SOL004 VNF package to the SVNFM
Ericsson Lab

COMPLETED

Note: The ETSI-Alignment package management test is completed

MAY 15TH








No,

CSIT Automation of use case targeted for G release

SO-2683 - Getting issue details... STATUS


Its CSIT testing will be implemented in the Guilin release. For Frankfurt, the test for defined test cases is completed.
27Merged with record 8

Merged with record 8

Merged with record 8Merged with record 8Merged with record 8







28xNF communication security enhancements.xNF communication security enhancements - Tests Description and Status

COMPLETED

COMPLETED



Tes Cases passed on RC0. Test status: xNF communication security enhancements - Tests Description and Status


Yes

CSIT's

DCAE
30

PNF Software Upgrade

  • PNF / PNF Software Upgrade with EM with Netconf
PNF software upgrade in R6 FrankfurtHuawei
INT-1212 - Getting issue details... STATUS

COMPLETED

COMPLETED



Test results:

Test Status of PNF S/W Upgrade with EM with Netconf/Yang interface

INT-1209 - Getting issue details... STATUS




315G - 5G NRM Network Resource Model (Configuration Mgmt)5G Network Resource Model (NRM) Configuration in R6 FrankfurtHuawei
INT-1245 - Getting issue details... STATUS

COMPLETED

COMPLETED




New documentation to be created, as it is a new use case for Frankfurt

INT-1514 - Getting issue details... STATUS




35Integration of CDS as an ActorIntegration TestingIntel / Windriver

COMPLETED

COMPLETED



Policy - CDS integration test was successfully completed in SB01 lab for vFW use case.

CLAMP - Policy integration test was successfully completed in SB01 lab for vFW use case.


Policy Framework

CDS

A&AI

CLAMP


37

Configuration with NETCONF in Frankfurt/R6

REQ-76 - Getting issue details... STATUS

REQ-140 - Getting issue details... STATUS

Detailed Steps carried out for performing E2E Testcases can be found at :  E2E Integration Testing for NETCONF over TLS Configuration- Test Case
Ajay Deep Singh

COMPLETED

COMPLETED



INT-1295 - Getting issue details... STATUS

Yes

AAF-Certservice,  SDNC,

Netconf-Pnp-Simulator




38

E2E Automation vLB w/CDS Use Case (Frankfurt)


NOTE: SO is using Config Assign & Config Deploy building blocks. 


SO Marco Instantiation using Controller Execution Building Block [new for Frankfurt] for vLB Instantiation will be a separate test case.[row below]

Steps:

Design Time

1) CBA Package onboarding CDS

2) SDC VSP, VF, Service Creation and onbaording for vLB.


Run Time: 

1) SO send Marcro requst to SDNC GR-API

2) SDNC GR-API send request to CDS, Netbox, Naming for instantiation resource auto resolution

3) SO sends request to CDS for Config Assign.

4) SO sends request to Openstack for vLB Instantiation 

5) SO send request to CDS for ConfigDeploy

Intel / Windriver

COMPLETED


COMPLETED






CDS, SDNC, SO, Policy, Naming MS, Netbox

SO issue with heat stack creation. Jira is open. 


SO-2802 - Getting issue details... STATUS

39

3rd Party Operational Domain Manager

Steps:

Steps to test SDC changes

SDC-2879 - Getting issue details... STATUS

Telstra

COMPLETED


COMPLETED


SDC-2879 - Getting issue details... STATUS






40

REQ-267 - Getting issue details... STATUS

CONFIGURATION & PERSISTENCY SERVICE R6


WinLAB

COMPLETED

MAY 23





Integration work will be part of OOF / SON / PCI Use Case.


will have the same integration status as that use case.

(Read the Docs entry in progress) being done under Integration Jira-1526

INT-1526 - Getting issue details... STATUS


SDN-C (CC-SDK) using MariaDBSandeep is leading the Integration & Development.
41

E2E Automation vLB w/CDS Use Case (Frankfurt)


SO Marco Instantiation using Controller Execution Building Block [new for Frankfurt] for vLB Instantiation.

Steps:

Design Time

1) CBA Package onboarding CDS

2) SDC VSP, VF, Service Creation and onbaording for vLB.


Run Time: 

1) SO send Marcro requst to SDNC GR-API

2) SDNC GR-API send request to CDS, Netbox, Naming for instantiation resource auto resolution

3) SO sends request to CDS for ControllerExecutionBB with scope of vnf and action of config-assign.

4) SO sends request to Openstack for vLB Instantiation 

5) SO send request to CDS for ControllerExecutionBB with scope of vnf and action of config-deploy.

Intel / Windriver

COMPLETED


COMPLETED






CDS, SDNC, SO, Policy, Naming MS, Netbox

NOTE: in order for this use case to work out of the box. The following patches need to be merged to frankfurt release:



 


Use cases without resources for Frankfurt
2Use Case: Residential Broadband vCPE (Approved)

vCPE Integration Test Case

Intel / Windriver


PROGRESSING <90%

???

During May 4 PTL meeting, Morgan Richomme reports that this issue may need to be de-scoped since there are no resources available for integration test.



Not restested as part of Frankfurt release


https://docs.onap.org/en/latest/submodules/integration.git/docs/docs_vCPE.htmlNo


75G - Configuration with NETCONF

5G - PNF Configuration via Netconf - Test Status

Intel/

Windriver


This item is duplicate.

Please see line #37 for work related to this feature in R6.





https://onap.readthedocs.io/en/latest/submodules/integration.git/docs/docs_5G_Configuration_over_NETCONF.html#docs-5g-configuration-over-netconf

Minor updates

Yes

14Change Management - Flexible Designer & Orchestrator

Steps:

1) Designing custom workflows with Workflow Designer

2) Distributing custom workflows to SO

3) Deploying the custom workflow in SO

4) Sending workflow metadata to VID

5) Triggering custom workflow execution from VID

6) Executing custom workflows in SO

Intel / Windriver
NOT A CANDIDATE FOR FRANKFURT




Not restested as part of Frankfurt release


1) Designing custom workflows with Workflow Designer – 100%

2) Distributing custom workflows to SO – Was 100% in Dublin Issues arose with SDC Distribution in El Alto and remain unresolved – 80% working now. However, SO does work properly with manual WF distribution and workaround notes are posted on the wiki

3) Deploying the custom workflow in SO – 100%

4) Sending workflow metadata to VID – 100%

5) Triggering custom workflow execution from VID – 100%

6) Executing custom workflows in SO – Execution mechanism 100%, Building Blocks – 60% (Had many issues with test environment & APPC blocking testing from Nov-Jan)

7) Pause for Manual Task – 100%





17Change Management - Schedule Optimization
Intel / Windriver

NOT A CANDIDATE FOR FRANKFURT




Not restested as part of Frankfurt release






29HPA vIPsecvIPsec HPA testingIntel / WindriverNot tested

Not restested as part of Frankfurt release




Pairwise testing
32TOSCA Compliant Policy typesPairwise TestingIntel / Windriver

COMPLETED

COMPLETED

COMPLETED

Recommended for a GO

#1 Can you please provide your tests results?

#2 Any automated tests?

Testing completed via CLAMP/Policy pairwise testing over the time period between M4 and RC1 in SB01/SB00.

Additional testing is covered via the vFW, Scale Out, vFW CDS use cases.

Automated test for vFW updated:

INT-1350 - Getting issue details... STATUS

No other automated tests for CLAMP as this was tested manually using CLAMP GUI.

REQ-21 - Getting issue details... STATUS




33Policy Update NotificationsPairwise TestingIntel / Windriver

COMPLETED

COMPLETED

COMPLETED

Recommended for a GO

#1 Can you please provide your tests results?

#2 Any automated tests?

Testing completed via POLICY/DCAE pairwise testing completed by RC0.


No automated tests.

REQ-25 - Getting issue details... STATUS




34CLAMP Deployment of Policies to PDP GroupsPairwise TestingIntel / Windriver

COMPLETED

COMPLETED

COMPLETED

Recommended for a GO

#1 Can you please provide your tests results?

#2 Any automated tests?

Testing completed via CLAMP/Policy pairwise testing over the time period between M4 and RC1 in SB01/SB00.

Additional testing is covered via the vFW, Scale Out, vFW CDS use cases.


No automated tests as this is done manually via the CLAMP GUI.

REQ-29 - Getting issue details... STATUS




36Component Upgrades to the new Policy Lifecycle APIPairwise TestingIntel / Windriver

COMPLETED

COMPLETED

COMPLETED

Recommended for a GO

#1 Can you please provide your tests results?

#2 Any automated tests?

Policy/CCSDK testing was successfully completed via pairwise testing in SB01 by RC0.

Policy/OOF testing successfully completed by RC1 and was done in SB01.

No automated tests.

REQ-162 - Getting issue details... STATUS




POLICY-2486 - Getting issue details... STATUS


Misc




















Robot Keyword Testing





init_robot










init
BDFOK







health
Integrated in gate

COMPLETED









eteHelm-k8.sh
BDF*OK



Not integrated in gate but onap-k8s and onap-helm (not based on Robot) Integrated in Gate


healthdist
Integrated in gate

COMPLETED









instantiateVFWCLGRA


BDFOK







demo-k8s.sh -n onap vfwclosedloop <png_ip>
BDFOK







instantiateVFWDTGRA
BDFOK







distributeVCPE
BDFOK







distributeVCPEResCust










sdc-dcae-d










vcpe.py










postinstall
Integrated in gate

COMPLETED









72 Hour Stability Runonboard/instantiate










closedloop










HTTP Certificate Expiry Test

(verify_cert.sh)



clamp 3/2020

dmaap 3/2020







Tobe integrated in gate, raise an error in CI when 1 of the certificates is about to expire (in 2 weeks?)




27Component/memory optimization: Ongoing Assessment
OOM




Addressed by OOM in Guilin


29S3P- Geo-Redundancy
Integration


Not tested as part of Frankfurt release
No resources


35Health Checks for PODSPercentage coverage of Health Checks for Running PODSIntegration




Hard to define...and to test


36


New Installation Tests in 4 labs


Intel/Windriver 
Integration













Reccurent activity















Orange  (Rocky)Morgan Richomme

Morgan Richomme
Ericsson Lab  (Rocky)



DT




DCAEGEN2-1539 - Getting issue details... STATUS


*: CI integration: the goal is to introduce the use case in CI daily chains for Frankfurt. Ths table could be completed with a CI dashboard where the use cases will be run every day.

As it should be runnable in any lab, some constraints need to be considered:

  • no proprietary VNFs                                            
  • use cases must be self-content , third party equiments may not be present in all labs.
  • infrastructure setup/teardown shall be clear: the use case must be runnable from a clean ONAP installation. These resources must be cleaned at the end of the test ,
  • results shall be pushed to a common DB. It is recommended ot use xtesting to run the tests (robotframework, python, bash, unit test drivers)