Assumptions:
- Release, Security and Documentation scopes are now tracked via JIRA
- Adoption to “Do not break the build” principle
- No Vendor equipment is required for this release
- No new VNF requirement identified by the project team
- Jenkins Jobs Failures are monitored and fixed by the project team
- Health check and regression tests issues are reported by the Integration Team
- Project Team defines their Sprint content based on TSC prioritization to meet the delivery deadlines
- Inform TSC about any descope content post-M1 before changing FixVersion
M1
updated Oct 25
- Define Frankfurt Scope with jira tickets labeled OR fixVersion
- Any Architecture changes (Y/N)? Yes then require a ArchComm review plan
- Any API changes Y/N
- Frankfurt Release Platform Maturity == Dublin goals - update M1 Target
- New 3rd party dependencies, new FOSS? Y/N (Seed Code)
- CII badging update
- Review code coverage goal vs. actuals
- Change build process to adopt new oparent, Portal SDK - Anything else?
- Fill in the Release Planning Template
- Assess Python3 migration status
- Assess Java 11 migration status
- Add project documents to document tracking table
M2/M3
- API docs complete
- Data Models (e.g, JSON, YANG, Swagger, etc.) shared with Modeling/Community
- Architecture Review complete (if required)
- No Gerrit requests older than 36 hrs.
- Provide docker to integration testing for Wave1: oParent, PortalSDK
- OOM port list update
- Fix any Integration blocker - Daily status updates on integration blockers, Highest/High issues
- Review and plan resolution of any License scan, security issues
- Update Frankfurt Risks
M4
- New 3rd party dependencies, new FOSS (final confirmation)
- License scan issues addressed
- Address all security issues
- All high/highest priority jira tickets addressed
- Update Frankfurt Release Platform Maturity, CII badging update - update M4 Result
- Test coverage goals complete
- No Gerrit requests older than 36 hrs.
- Integration weather board update
- Update Frankfurt Risks
RCx
- All high/highest priority jira tickets addressed
- Remaining License scan, security critical issues addressed
- Update Release note and documentation
- Docker images “Release” dues
- Project specific test plan for El Alto completed
- Update Frankfurt Risks
- Integration Weather Board complete
- Versioning at the project level
- Check the certification expiry of your application. It should be valid for the next 9 months after RC0.
Sign-off
- Remaining high/highest priority jira tickets addressed or workaround documented
- Close/move all open/in-process jiras to a future release
- Integration "Sign-Off" on Docker images “Release”
- Release notes and documentation completed
- OOM tag release and version in helm chart
- Update the Frankfurt Release Key Updates