DRAFT PROPOSAL FOR COMMENTS

The following items are expected to be completed for the project to Pass the M2 Functionality Freeze Milestone.

M2 Release Functionality Freeze Milestone definition.


Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
  2. Fill out the Yes/No column
  3. Provide link to evidence (when necessary)
Practice AreaCheckpointYes/NoEvidence - CommentHow to?
Product Management

Are all provisional APIs interface (stub) been defined (at beta-quality level)? 

WIP


Is there a final list of externally consumable APIs available?

Yes

https://onap.readthedocs.io/en/latest/submodules/dcaegen2.git/docs/sections/offeredapis.html

For all completed Sprints, have Sprint Backlog Stories been marked as "Done" in Jira?

Yes

Getting issues...


Difference between a Product and Sprint Backlog

Are all tasks associated with the completed Sprint Backlog Stories been marked as "Done" in Jira?

Yes
 

Getting issues...


If applicable to your project, has your team been able to clear the project' blockers? If not provide status on the plan to close the blocker(s).YesDCAEGEN2-1191 - Patch submitted
What new features or changes to existing features in this project scope need to be communicated to VNF Providers? List the changes in the Evidence tab.Yes

VES Collector - Authentication enhancement



If yes to the previous question, have these been communicated to the VNF Requirements project? YesVNFRQTS
Release Management

Have all source code files been updated with License Apache 2 header?YesNew contribution pending.Specific rules and instruction are available in ONAP wiki.
Has the year format in copyright header of all source code files been updated? (Rules for new files created in 2019 and existing files modified in 2019 are different)Yes
Guidance on year format
In case source code can't be edited, has a "License.txt" file been placed at the root directory for which the license is applicable?

Yes



Guidance for source code file that can't be edited
(a) Has the Project Team added appropriate license and copyright notices to all ONAP source code and documentation files, where possible for the particular file format?Yes

(b) Has the Project Team reviewed and understood the most recent license scan reports from the LF, for both (a) licenses within the codebase and (b) licenses for third-party build time dependencies?Yes

For both (a) and (b) questions, have all high priority non-Project Licenses been either removed, planned for removal before code freeze, or escalated as likely exception requests?Yes

Have all API projects dependencies been captured?

YesDCAE R4 M1 Release Planning#APIIncomingDependenciesThe source of information for the API dependency is the "API Incoming Dependency" of the M1 Release Planning deliverable. Please update the source accordingly, and let The Release Manager aware of the changes.
DevelopmentFor new projects approved for this release, have all defined repositories source code been placed into Gerrit?No

Repository created; seed code delivery in-progress 

  • dcaegen2/services/son-handler


Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)No

Yes for all but new components; will be addressed by M4

Goal: 52%

Guidance on Code Coverage and Static Code Analysis

Tools: Sonar

Is there any binaries (jar, war, tar, gz, gzip, zip files) in Gerrit project repository?NoExcept new components which are WIPRefer to CI Development Best Practices
Could you ensure that all proprietary trademarks, logos, product names, company name, etc. have been removed? All ONAP deliverables must comply with this rule and be agnostic of any proprietary symbols.Yes

Is there any pending commit request older than 36 business hours in Gerrit?Yes
https://gerrit.onap.org/r/#/q/status:open+topic:info-file (22) Pending LF update; rest are pending submitter update (merge conflict and/or publish pending)
Have all the Jenkins jobs successfully passed (Merge-Jobs)?No

Except new components which are WIP

https://jenkins.onap.org/view/dcaegen2/


Are all snapshot binaries available in Nexus?NoExcept new components which are WIP
Integration and Testing  Have functional test cases been documented in wiki?Yes

https://wiki.onap.org/display/DW/5G+-+Real+Time+PM+and+High+Volume+Stream+Data+Collection

PM Mapper/DFC - https://wiki.onap.org/display/DW/5G+-+Bulk+PM

3GPP PM Mapper Testcases & Status

5G SON-Handler - https://wiki.onap.org/display/DW/OOF-PCI+Use+Case+-+Dublin+Release+-+ONAP+based+SON+for+PCI+and+ANR

BBS Usecase - BBS Notifications#TestCases

Regression - DCAE Testplan (Regression)



Have you implemented in Jenkins at least 1 functional test case for each of the project repository?Yeshttps://jenkins.onap.org/view/dcagen2/job/dcaegen2-master-csit-testsuites/

As an example (provided by Integration Team)


Has the project code successfully passed the Build process?YesExcept new components which are WIP

Goal is to ensure your project latest commits have not broken the build.

DocumentationHas the team identified and outlined the set of documentations to be delivered in this Release?Yes