Agenda
- Status and Stucks
- Technical Discussion
- Making the PTL Happy
Notes
- Status and Stucks
Current POMBA Dublin Stories (Logging Project) -
Current Code Inspections
- POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
General Status
- Dublin
- Tasks to be closed off (just a technicality):
- Stories in progress: All 3 of them will be delivered by Feb-08.
- Stories to be formally verified before closure:
- - LOG-778Getting issue details... STATUS
- - LOG-763Getting issue details... STATUS
- - SDNC-475Getting issue details... STATUS : For network resource only and should be split into Network Discovery and ND context builder.
- - LOG-779Getting issue details... STATUS
- - LOG-404Getting issue details... STATUS
- Stories closed since last meeting:
- Bugs to enter:
- Latest security scan results show ~9 medium issues that should be recorded (but aren't severe enough to merit immediate work).
- Bugs entered in last week:
- Bugs in progress:
- Bugs to be verified:
- Bugs closed off since last meeting:
- Dublin
- Technical Discussion
- Cross context builder dependencies, documented
- Note we need to be careful about breaking POMBA when in the middle of incremental updates, where OOM isn't yet done.
- Organizing Models and Swaggers between releases
- Summary table
- POMBA Releases
- Note technically there was Swagger for the network discovery API in Casablanca, but it could not be used out of the box and has changed so much, we decided to remove it.
- POMBA Releases
- Basic navigation should take us to current. Need to verify this
- Summary table
- Consider demo schedules
- J. Ram Balasubramanian will forecast demos as development progresses
Data Dictionary & Network Discovery- Dec 20Done
- L2 Network data
- Let's demo with some rules.
- If we want validation run on new data, then Feb 21st makes more sense
- Additional enhancement - March 21st
- J. Ram Balasubramanian will forecast demos as development progresses
- Should ping the automation team on POMBA usage
- Chesla to ping Brian.
- Making the PTL Happy
- Dublin
- Should look at milestones and ensure we are in good shape.
- Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
- Prudence is supporting Michael for this activity.
https://wiki.onap.org/display/DW/Logging+Dublin+M1+Release+Planning
- Functionality freeze Feb 14
- Not sure if this was impacted by M1 slip - nope - still the 14th
- API freeze is March 14th.
- Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
- Should look at milestones and ensure we are in good shape.
- Dublin