Agenda
- Status and Stucks
- Technical Discussion
- Making the PTL Happy
Notes
- Status and Stucks
Current POMBA Dublin Stories (Logging Project) -
Current Code Inspections
- POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
- Status: RED – Michael O'Brien will need to address what looks like some outages in the tool
- Something broken? Not giving update updates. Still broken as of last night.
- General Status
- Casablanca
- Bugs in progress:
- Bugs to be verified:
- Bugs closed off:
- Dublin
- Stories in progress:
- Bugs in progress:
- Bugs to be verified:
- Casablanca
- Technical Discussion
- Integration Team discussion
- When we know the Openstack/network discovery info will work in ONAP, we shall reach out to Brian and the Integration team again.
- The logs are broken, which makes it harder to debug and test.
- The logs are broken, which makes it harder to debug and test.
- How to test L2 Fabric
- Some of that information may be not be available in ONAP
- But the resources will be, even if for other reason.
- When we know the Openstack/network discovery info will work in ONAP, we shall reach out to Brian and the Integration team again.
- Consider demo schedules
- David Stangl has identified some timeframes where demos would probably make sense based on current forecast
- Data Dictionary - end of Dec?
- Technically that would be Dec 20.
- Also demo network discovery of VM info using native code as part of end to end flow.
- L2 Network AVPs - beginning of Feb?
- Set a more specific date in January
- Network Audit - end of Feb?
- Data Dictionary - end of Dec?
- David Stangl has identified some timeframes where demos would probably make sense based on current forecast
- Integration Team discussion
- Making the PTL Happy
- ONAP Casablanca Maintenance?
- Consider porting bugs into maintenance (add label for candidates)
- Only high and highest ones. Ones that impact other components, prevent POMBA from launching or the audit to even start.
- Consider porting bugs into maintenance (add label for candidates)
- Dublin
- Should look at milestones and ensure we are in good shape.
- Feature commitment Jan 17
- Functionality freeze Feb 14
- API freeze is March 14th.
- Should look at milestones and ensure we are in good shape.
- ONAP Casablanca Maintenance?