Tracking Table
Project Name | Document Title | Document Owner (name - use @ notation) | Current Document State (as of M1) Choices:
| Activity Planned for Release Choices:
| Preliminary Documentation New docs or new projects ONLY (enter "N/A" if not applicable, or link to gerrit if completed) | Attended Doc Hackathon 1 on March 11 (Document owner must attend at least one hackathon) (fill in green checkmark if attended) | Attended Doc Hackathon 2 on March 25 (Document owner must attend at least one hackathon) (fill in green checkmark if attended) | Link to Final Documentation in ReadTheDocs (stable/guilin branch) | Reviewed by the doc project (reviewed means release related content. Such as release notes and release name were applicable) By best effort! |
---|---|---|---|---|---|---|---|---|---|
M1 | M2/M3 | Post-M4 | RC2 | ||||||
Procedure
M1
- Find JIRA task attached to M1 Epic for your project, if you haven't already done so.
- In the table above, fill in
- project name
- doc title,
- doc owner (use Confluence @ notation for name, e.g., David McBride)
- current doc state
- activity planned for release
- Update status of JIRA task as Done
M2/M3
- Find JIRA task attached to M2 Epic for your project, if you haven't already done so.
- Note that this task applies to new documents only (i.e., "New" in Current Document State column). If this is not a new document, just enter "N/A" in the Preliminary Documentation Completed column in the table above.
- For new documents, at a minimum create a placeholder document (e.g., document with a title, or an outline), and commit to the repo. Add a link to the gerrit to the Preliminary Documentation column in the table above.
- Update the status of the JIRA task as Done.
Post M4
- Find the dates for the two documentation hackathons.
- The document owner should plan on attending at least one of the two hackathons.
- Enter a green checkmark in the appropriate column in the table above for the hackathon that was attended.
RC2
- Find JIRA task attached to RC0 Epic for your project, if you haven't already done so.
- Add a link to the document in ReadTheDocs in the appropriate column in the table above.
- Update the status of the JIRA task as Done.