1. Introduction
This is the integration test cases for OSAM use case.
2. Scope
The integration test case for OSAM use case, it includes VNF and PNF design from SDC, PNF registration, PNF activation, VNF instantiation and closed loop for VNFs
3.Terms, definitions and abbreviations
Abbreviation | Full Name |
PNF | Physical Network Function |
VNF | Virtual Network Function |
GUI | Graphic User Interface |
GW | Gateway |
SEBA | SDN-Enabled Broadband Access |
4. Test Framework
TODO here: Add image to show test framework... can use architecture picture...
Module Introduction
Module | Function |
OSAM Core | Seba specific operations are done on this VNF |
OSAM GW | Adapter between SEBA and OSAM Core |
ONAP | The ONAP system for automation operation |
5. Test Description
Test cases for ONAP, existing VF functions are going to be used for OSAM GW and OSAM Core. OSAM GW and OSAM Core specific designs should be applied also designed VFs should be deployed and their LCM should be managed as well. ONAP's PNF functionally such as PNFD at onboarding time, PNF registration, PNF instantiation and PNF activation should be tested for SEBA.
5.1 Test Accounts
Name | Responsibility | Account |
Administrator | Responsible for system management; Personnel permission configuration; ONAP external system registration; Operational life cycle management | demo/demo123456! |
Designer | Service template design | cs0008/demo123456! |
Tester | Service template test | jm0007/demo123456! |
Governor | Service template approve | gv0001/demo123456! |
Operator | Service template distribution | op0001/demo123456! |
6. SDC Resource Design
6.1 OSAM Core Resource Design
Test NO: | TEST-01 |
Project: | SDC |
Sub Project | Resource import for OSAM Core |
Objective: | Support to import the resources for OSAM |
Operator: | Designer, Tester |
Pre-conditions: |
|
Test Step:
| |
The Result
| |
Observation: We can find a new resource for OSAM GW in SDC catalog. |
6.2 OSAM GW Resource Design
Test NO: | TEST-02 |
Project: | SDC |
Sub Project | Resource import for OSAM GW |
Objective: | Support to import the resource for OSAM |
Operator: | Designer, Tester |
Pre-conditions: | 1.Required Tosca type should be ready for OSAM GW |
Name
Responsibility
Account
Administrator
Responsible for system management; Personnel permission configuration; ONAP external system registration; Operational life cycle management
demo/demo123456!
Designer
Service template design
cs0008/demo123456!
Tester
Service template test
jm0007/demo123456!
Governor
Service template approve
gv0001/demo123456!
Operator
Service template distribution
op0001/demo123456!