The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.
M3 Release Architecture Milestone overview is available in wiki.
Usage
- Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
- Fill out the Yes/No column
- Provide link to evidence (when necessary)
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Architecture | Has the Project team reviewed the APIs with the Architecture Committee (ARC)? | Review is scheduled on Aug 29th | Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough. | |
Is there a plan to address the findings the API review? | Once review is done, we will update | Link to plan | The plan could be as simple as a Jira issue to track the implementation of findings or a documented plan within the wiki. | |
Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval? | Yes | NA | In the case some changes are necessary, bring the request to the TSC for review and approval. | |
Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone? | NO | If Yes, please a link to the evidence of these changes. | Critical point to understand is that change is inevitable, and that right timing and clear communication to the community will ease the process of accepting changes. | |
Provide link to the API Documentation. | AAF API | |||
Release Management | Are committed Sprint Backlog Stories been marked as "Done" in Jira board? | Yes | https://jira.onap.org/secure/RapidBoard.jspa?rapidView=69&view=planning&selectedIssue=AAF-37&versions=visible&epics=visible | |
Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira? | Yes | https://jira.onap.org/secure/RapidBoard.jspa?rapidView=69&view=planning&selectedIssue=AAF-37&versions=visible&epics=visible | ||
Have all findings from previous milestones been addressed? | Jenkins Jobs, Releasing Artifacts to Nexus, Sonar and Implementing automated functional test case is pending | Provide link to JIRA findings | ||
Development | Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar) | In Progress | Goal: 30-50% for Incubation project | Guidance on Code Coverage and Static Code Analysis |
Is there any pending commit request older than 36 Business hours in Gerrit? | No | |||
Are all the Jenkins jobs successfully passed ( Merge-Jobs)? | In Progress | Provide link to evidence | ||
Are all binaries available in Nexus? | No | Provide link to evidence | ||
Integration and Testing | Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins? | No | Provide link to evidence | |
Has the project code successfully passed the Daily Build process? | In Progress | Goal is to ensure the latest project commit has not broken the Integration Daily Build |