All related issues are listed underĀ JIRA EpicĀ
JIRA story | Task | ONAP Component | Task Description | Committers | Status | Notes |
---|---|---|---|---|---|---|
VNF CSAR defintion | SDC |
| Done | |||
E2E service CSAR definition | SDC |
| Done | |||
GUI WAN network design support | SDC |
| David Shadmi | Done | In R1, WAN design part is done through importing Network Service templates which define all parameters needed for WAN underlay and overlay networks. | |
GUI support on E2E service design | SDC |
| David Shadmi | Done | Will add a link to the meeting recording which has a simple demo of VoLTE E2E service design | |
VoLTE service instantiation sequencing | SDC |
| Done | SDC can support Dependency construct already | ||
Support TOSCA VNFD import | SDC |
| High Risk |
| ||
vEPC service design | Integration |
| In progress | Need to discuss with integration team and come up with different design options | ||
vIMS service design | Integration |
| Yang Xu | In progress | ||
A&AI schema change to support ESR | A&AI |
| Done | |||
A&AI schema change to support VFC | VFC |
| In progress | |||
Workflow design and implementation | SO |
| In progress | Yang Xu Need to confirm with SO team they can use the dependency construct | ||
VFC service instantiation sequence | VFC | Yan Yang | ||||
DG design and implementation for WAN service | SDNC |
| High risk | Integration with the vendor's PE and DC Gateway is not tested yet | ||
Holmes Correlation Policy | Holmes |
| Risk | Developement is delayed. Not in MVP | ||
Closed loop configuration | CLAMP |
| Risk | Developement is delayed, not in MVP | ||
Policy design | Policy |
| @integration | In progress | Integration team needs to talk to Policy team to see how to define the policy in GUI | |
Usecase UI development | Usecase UI |
| Risk | Development is delayed, and repo is still empty as of September 5, 2017. Not in MVP |