We will start our meetings by mentioning the project's Antitrust Policy, which you can find linked from the LF and project websites. The policy is important where multiple companies, including potential industry competitors, are participating in meetings. Please review and if you have any questions, please contact your company legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.
SO-3467
-
Getting issue details...STATUS
,
SO-3468
-
Getting issue details...STATUS
- also in Honolulu? If yes then please document them as known issue in Honolulu release.
Tagging?
PTL responsibility. Can file ticket with IT for assistance.
E2E Network slicing feedback - There are 5 tracks:
Closed Loop, RAN NSSMF and Transport NSSMF tracks (3) are in good shape, and most of the important tests are completed. There is 1 blocking issue for Transport NSSMF which we are trying to overcome with a workaround. The remaining tests shall be carried over to Istanbul.
Core NSSMF track – some parts are yet to be tested. This testing will be carried over to Istanbul.
NSMF track - a few important tests are in progress and we expect to know the outcome later today/early tmow morning. In any case, the remaining tests shall be carried over to Istanbul.
We will submit updates to the use case documentation tomorrow, based on (3) mainly as well as the not-completed tests of remaining tracks.