zoom bridge: https://zoom.us/j/283628617

Duration 60 minutes

DurationAgenda ItemRequested byNotes / Links
START RECORDING
30min

Dublin end game plans

RC1 - May 16th

RC2 - May 30th (Euro holiday)

Sign-off - June 6th

RC1 Follow-up: Deliverables for RCx Milestone Checklist Template


5 minImage release plan before 6/6

Unreleased images used in OOM: http://onapci.org/

RC2 image release by this Thursday 5/23

No more image release accepted by Integration after 5/23, unless explicitly asked by Integration and those images can ONLY contain bug fixes required by Integration

After the 23rd, High/highest priority, integration tag only will be accepted into the test images.

Please do not spin up new instances in the WR lab as the resource consumption inhibits integration progress.

20 minNexus → Docker hub MigrationBrian Hedstrom Paul-Ionut Vaduva Jessica Gonzalez
10 minAlternatives Vulnerability fixes delivery vehicle - El Alto early drop vs. Dublin Maint Release

We need to repair the vulnerabilities w/in 60 days of disclosure for CII Badging. 

Problem statement: What is the preferred method of delivering critical fixes atop Dublin within 60 days?

Some alternatives:

  1. Mid-El-Alto release candidate test cycle to validate component releases?
  2. Dublin maintenance release?

Former user (Deleted) to send out email on the topic asking for feedback.

10minSECCOM update - unresolved CVE review & other security followups

Still some updates expected for known vulnerabilities from: Holmes, Logging, Portal, SO, UUI, VFC and VNFSDK. PLEASE TAKE SOME EFFORT... 

TSC has approved pen tests pre-disclosure process - > to work on the general disclosure way with LFN team.

We would like to share OJSI tickets learnings with PTLs community.

Release notes will be developed and submitted to the project PTLs for merging. Please review and +1 these requests.


Events reminderFormer user (Deleted)

https://lists.onap.org/g/onap-tsc/topic/june_ddf_registration_is_now/31435252?p=,,,20,0,0,0::recentpostdate%2Fsticky,,,20,2,0,31435252

Zoom Chat Log 


Action Items

  • 2/11: Migrate Docker image releases from Nexus3 into Docker Hub (Architecture Independence) by Dublin M4. 
    <2-15-2019> Preparing a preso for review of all known infrastructure change requests for review at PTL meeting 2-25-2019
    <2019-04-08: global-jjb progress report: start on DCAE soon - focus on El Alto delivery (precursor to Dockerhub)<2019-04-22 - Using mvn staging plugins to deploy - unfort many of the changes need to be in the source code to insure the job is running>
  • Tlab persistent storage IO architecture Rich Bennett 
    Request from Rich Bennett about Storage/Persistent Data Architecture Plan/PTLs - Single NFS server? 
    <2019-04-22: performance issues with old config - have bare metal cluster - - want to bring in more realistic operational aspects to the testing - network storage vs direct, would like to place modules in isolation into the environment. Evaluating the utility of testing this way. 
  • How to consume Alpine? Adolfo Perez-Duran (Deactivated)
    Meeting organized in May - https://wiki.onap.org/display/DW/TSC+2019-05-16