Duration 90 minutes

Agenda ItemsPresented byTimeNotes / LinksJIRA Tasks
Casablanca Release Status30 mins

New reporting proposal & Latest status

Integration Status

Notes:

  • Legend for Releae status review: RED- require TSC support/attention; Yellow - not perfect but team is working on it ; Green - on track

  • For platform maturity, T is the target level and A is the achieved level
  • Action Items:
    • Review Casablanca Platform Maturity scorecard with PTLs
    • Jason & Securtiy Subcommittee to work with PTLs and assess if current S3P status acceptable or not - feedback expected for RC0
    • Legend to be added to Casabkanca Platform Maturity
  • PTL Prioritization:
    • RC0: Healthcheck, pair-wise, AAF integration, vFW, vDNS
    • RC1: Stability, Resiliency
  • Overall Status: Expected next week "green status" for all healthchecks


Any Infrastructure Improvement/Plan

Linux Foundation

10 mins

Lesson Learned - Nexus?

Notes:

  • Action Item for LF (Jess): provide ETA concerning Nexus issue by Oct 5th - short term solution to unlock PTLs and long term (extension of capacity)

Incoming ONAP Events10 mins
  • F2F Architecture/(Modeling) Meeting in Montreal
    Oct 29nd-31st
  • V2F Dublin Release Meeting
    Week of Nov 19th?
    • Notes:
      • F2F Event Week of Jan 7th, hosted by Nokia? 
      • Action Item (Catherine): Create Doodle to decide about the V2F Dublin Release Meeting date

TSC-10 - Getting issue details... STATUS


TSC-7 - Getting issue details... STATUS

TSC Activities and Deadlines15 mins

TSC Transformation?

TSC Dashboard Presentation (https://jira.onap.org/projects/TSC/summary)

Urgent activities:

  •     2019 Budget Plan by Oct. 17th Board Meeting
  •     TSC Chart by Oct 18th

TSC-8 - Getting issue details... STATUS

TSC-1 - Getting issue details... STATUS

TSC-11 - Getting issue details... STATUS

TSC-14 - Getting issue details... STATUS

New Task Force Request (s)15 mins

What do we want to accomplish with Dublin to support our primary goal:

Accelerate adoption of ONAP in production.

  • Notes:
    • (Michael): acumos consumes artifacts and architecture from ONAP - raised JIRA to formalize the sync (TSC-15)
Dublin Areas - Target: Oct 25th.
  • Project enhancements (PTLs)
  • Non Functional requirements including Operational Readiness
    Definition of ONAP Orchestrator Functionalities
  • Project & Subcommittee Best Practices (i.e. CI/CD, E2E etc)
  • Use Cases
  • Deployment Capabilities - ONAP Self-Serve
  • Release Packaging

In progress

TSC-13 - Getting issue details... STATUS


Additional housekeepingLinux Foundation10 minsNo update this week


-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------


Agenda ItemRequested byNotes / Links
Housekeeping


Release Status


Subcommittee / Coordinator Update

What are ONAP/an orchestrator core functionalities?Alexis de Talhouët

Goal is to identify the main functionalities required for orchestration, and have community focus on them.
Goal is not to park other functionalities, but to have good awarness and focus on the critical gaps being currently there.

ONAP as self-serve platformWhat TSC think about self-serve for ONAP. Current state of ONAP. Next steps. Goals, etc...
VF2F in NovemberAlla.Goldnernecessity of VF2F meeting in preparations for Dublin Release
2019 Budget Plan

Looking to have this for the Oct. 17th Board Meeting

TSC-8 - Getting issue details... STATUS

InfrastructureAlexis de TalhouëtState of ONAP's infra. Blocking issues. Update from LF.



Zoom Chat Log 





Zoom Attendance Log 



Action items

  • Casablanca Status: Review Casablanca Platform Maturity scorecard with PTLs
  • Casablanca Status: Jason & Securtiy Subcommittee to work with PTLs and assess if current S3P status acceptable or not - feedback expected for RC0
  • Casablanca Status: Legend to be added to Casabkanca Platform Maturity
  • LF (Jess): provide ETA concerning Nexus issue by Oct 5th - short term solution to unlock PTLs and long term (extension of capacity)
  • (Catherine): Create Doodle to decide about the V2F Dublin Release Meeting date