Official Minutes: TSC Aug 24, 201713:21:46 UTC
Recording
Zoom chat log
Discussion items
Duration | Agenda Item | Requested by | Notes / Links | ||||
---|---|---|---|---|---|---|---|
START RECORDING | |||||||
60 | See table below | Gildas Lanilis Gmailsee table below |
| ||||
15 | R2 Architecture Review | Eman Gil | not addressed- roll over to next week | ||||
10 | ONAP University | not addressed- to be covered in email | |||||
5 | Round table | not addressed |
...
Project | #1 On Track for M4 Sept. 14th ? | #2 Addl Time Required? | #3 What Can Be De-scoped? | Feedback |
---|---|---|---|---|
A & AI | On Track | stories exist, builds and jenkins issues are the new ESR items, Work on blockers are in progress. Babel repo is for Beijing release content. | ||
Application Authorization Framework | On Track | com.att package structure impacting jekins will be addressed by EOW. | ||
APPC | On Track | Plan in place to address scope changes. API Doc will be posted tomorrow. | ||
CLAMP | On Track | May be minor change requests but should be able to address. | ||
Common Controller SDK | On Track | |||
DCAE | Potential risk | Risk is related to blockers- Also Lusheng Ji -2 open tickets did not get conformations. Most dcaegen2 code not java code | ||
DMaaP | On Track | Testing concerns with DCAE, com.att to onap issue, have requested 5 new repos. | ||
Documentation | On Track | need support of other projects. | ||
External API Framework | No Representation | |||
Holmes | At Risk | Detailed API info from DCAE must be delivered by end of next week to meet deadline. | Blocker from DCAE will prevent M4 - (info submitted into gerrit by DCAE yesterday) | |
Integration | On Track | more information will be presented at next week's TSC meeting (added to 8/31 agenda - kep) | ||
Logging Enhancements Project | On Track | Primarily being delivered in other project's repos. | ||
Microservices Bus | On Track | but many issues to resolve, including some sonar problems | ||
Modeling | On Track | Blocked on scan results | ||
Multi VIM/Cloud | On Track | |||
CLI | On Track | |||
ONAP Operations Manager | On Track | |||
ONAP University | Off Track | No PTL. minimal progress | ||
Usecase UI | No Representation | |||
Policy Framework | At Risk | 2 weeks from whenever we get the answer from AAI | Would need to descope any control-loop use case - not a real option. | Raising a blocker for AAI - if not answered by end of next week M4 will not be met. |
Portal Platform | On Track | |||
SDN-C | On Track | |||
Service Design & Creation | Potential Risk | A number of issues are still present. | ||
Service Orchestrator | Off Track | Need 2-3 weeks | Desope not possible | workflows, at&t seed code migration, and misunderstandings. Specific details to be provided. |
VF-C: Virtual Function Controller | On Track | blocker w/ SDC being worked. | ||
VID | On Track | |||
VNF SDK | On Track | ICE code will be unavailable- have descoped HEAT validation for R1 as a result | Waiting on scan of VES code. | |
VNF Requirements | Highly At Risk | Tool issues must be resolved immediately to meet M4. | New blocker raised pending Documentation tool chain issues. Documents are failing to propagate | |
VNF Validation Program | Off Track | PTL out on leave- Steve W. now filling the void - project status being evaluated. |
...