Gliffy |
---|
size | 1200 |
---|
name | BBS - DevelopmentPlan |
---|
pagePin | 310 |
---|
|
Lead | Start | End | Status |
---|
1 | Requirement Analysis |
|
|
|
1.1 | Finalize BBS architecture | Mon 11.26.18 | Tue 12.11.18 | Status |
---|
colour | Green |
---|
title | Completed |
---|
|
|
1.2 | Building Team | Mon 11.26.18 | Wed 12.05.18 | Status |
---|
colour | Green |
---|
title | Completed |
---|
|
|
1.3 | Create Epics In Community JIRA | Tue 12.11.18 | Fri 12.21.18 | |
YellowOpen |
1.4 | Create user stories In Community JIRA | Fri 12.21.18 | Tue 12.25.18 | |
YellowOpen |
1.5 | Make Workloads, Acceptance criteria, Plan, Dependencies | Tue 12.25.18 | Mon 1.07.19 | |
YellowOpen |
1.6 | Low Level Design (Output specification for project design to review) 1. LLD for SDN-C & Access SDN M&C 2. LLD for SDN-C & Edge SDN M&C 3. LLD for VES Event definition 4. LLD for topology discovery from SDN M&C 5. LLD for External API 6. LLD for PRH enhancement
| Mon 1.07.19 | Mon 1.14.19 | |
NOT YET STARTED |
1.7 | Low Level Design review | Mon 1.14.19 | Thu 1.17.19 |
| |
1.8 | Model freeze | Mon 11.26.18 | Tue 12.11.18 | Status |
---|
colour | Green |
---|
title | Completed |
---|
|
|
1.9 | Model review | Tue 12.11.18 | Tue 12.18.18 | |
YellowOpen |
1.10 | Model pushed to the community | Thu 1.24.19 | Tue 2.05.19 |
Status |
---|
title | NOT YET STARTED | |
1.11 | API freeze | Tue 12.18.18 | Tue 12.25.18 | |
NOT YET STARTED |
1.12 | API review | Tue 12.18.18 | Tue 12.25.18 |
Status |
---|
title | NOT YET STARTED | |
1.13 | API pushed to he community | Thu 1.24.19 | Mon 3.04.19 |
| 2 | Coding | 2.1 | |
2 | Coding |
|
|
|
2.1 | Code Checkpoint 1 |
| Thu 3.07.19 |
|
2.2 | Code Checkpoint 2 |
| Thu 3.14.19 |
|
2.3 | Code freeze | Tue 12.25.18 |
Fri 208 | 24 | Weekly Code review | Tue 12.25.18 | Fri 2.08.19 |
| 35 | Unit test | Tue 12.25.18 | Fri 2.08.19 |
Status |
titleNOT YET STARTED | 46 | Code pushed to the community | Tue 12.25.18 | Thu 3.28.19 |
| |
3 | Testing |
|
|
|
3.1 | E2E Test design and demo strategy | Mon 1.07.19 | Wed 1.16.19 | |
YellowOpen |
3.2 | E2E Test design and demo strategy review | Wed 1.16.19 | Fri 1.18.19 | |
NOT YET STARTED |
3.3 | Internal Demo review | Mon 1.07.19 | Tue |
115 Status |
titleNOT YET STARTED | |
3.4 | Develop test plan | Fri 2.08.19 | Tue 2.12.19 | |
NOT YET STARTED |
3.5 | Project Test case output | Fri 2.08.19 | Tue 2.12.19 |
| |
3.6 | Project Interface self test | Fri 2.08.19 | Wed 2.27.19 |
status |
|
3.7 | Integration test plan | Fri 1.18.19 | Fri 1.25.19 | |
NOT YET STARTED |
3.8 | Integration Test case output | Fri 1.25.19 | Sat 1.26.19 |
| |
3.9 | Integration test | Fri 2.08.19 | Sat 3.09.19 | |
NOT YET STARTED |
3.10 | Internal Demo Show Round1 | Mon 3.11.19 |
Wed 13 | |
3.11 | Internal Demo Show Round2 | Mon 3.18.19 |
Wed 20titleNOT YET STARTED4Lab Setup |
4.1 | Development Environment (CI/CD, Code repo) | Mon 11.26.18 | Fri 12.07.18 | |
YellowOpen |
4.2 | Development Environment (local env, local test env) | Mon 11.26.18 | Fri 12.07.18 | |
YellowOpen |
4.3 | Detailed lab topology (wiring diagram) | Wed 12.26.18 | Wed 1.09.19 | Status |
---|
colour | Green |
---|
title | Completed |
---|
|
|
4.4 | Detailed lab topology (wiring diagram) review | Wed 1.09.19 | Wed 1.09.19 | |
YellowOpen |
4.5 | Material ready | Wed 12.26.18 | Wed 1.09.19 | |
NOT YET STARTED |
4.6 | Demo Lab setup | Fri 2.01.19 | Mon 2.25.19 | |
YellowOpen