Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Info
titleInfo

Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
Use the Wiki to document the release plan. Don't provide PowerPoint.
Use as much diagrams and flow charts as you need, directly in the wiki, to convey your message.

Table of Contents
outlinetrue

Overview

Project NameEnter the name of the project
Target Release NameBeijing
Project Lifecycle StateIncubation
Participating Company China Mobile, ZTE, Huawei, Raisecom

Scope

What is this release trying to address?

Describe the problem being solved by this release.

...

  1. Support NS/VNF scaling
  2. Provide Monitor GUI for VM alarm and performance
  3. Integration with Image Management Project
  4. Integration with OOM/Logging

Use Cases

Describe the use case this release is targeted for (better if reference to customer use case).

  1. Use Case: VoLTE(approved)
  2. Enterprise CPE(stretch goal)

Minimum Viable Product

Describe the MVP for this release.

...

Integration specification for OOM/Logging

Functionalities

List the functionalities that this release is committing to deliver by providing a link to JIRA Epics and Stories. In the JIRA Priority field, specify the priority (either High, Medium, Low). The priority will be used in case de-scoping is required. Don't assign High priority to all functionalities.

...

Functionality Name

In or Out

Priority

Stretch

Image mangement Integration

In

M

Integration with Image Management

Logging Integration

In

M

Integration with Logging

Epics

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = usecaseui and issuetype in (epic) AND issuetype = Epic AND status = "To Do" AND resolution = Unresolved AND fixVersion = "Beijing Release"
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

Stories

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = usecaseui and issuetype in (story) AND issuetype = Story AND fixVersion = "Beijing Release"
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

Longer term roadmap

Indicate at a high level the longer term roadmap. This is to put things into the big perspective.

Release Deliverables

Indicate the outcome (Executable, Source Code, Library, API description, Tool, Documentation, Release Note...) of this release.

Deliverable Name

Deliverable Description

Service LCM Portal

Providing GUI of service life cycle management

VNF Monitor Portal

Providing GUI for VNFs alarm and performance

VM Monitor Portal

Providing GUI for VMs alarm and performance

Sub-Components

List all sub-components part of this release.

...

Sub-components are repositories and are consolidated in a single centralized place. Edit the Release Components name for your project in the centralized page.

Architecture

High level architecture diagram

At that stage within the Release, the team is expected to provide more Architecture details describing how the functional modules are interacting.

Indicate where your project fit within the ONAP Archiecture diagram.

Image RemovedImage Added

Block and sequence diagrams showing relation within the project as well as relation with external components are expected.

Anyone reading this section should have a good understanding of all the interacting modules.

Image RemovedImage Added

Platform Maturity

Refering to CII Badging Security Program and Platform Maturity Requirements, fill out the table below by indicating the actual level , the targeted level for the current release and the evidences on how you plan to achieve the targeted level.

AreaActual LevelTargeted Level for current ReleaseHow, EvidencesComments
Performance01Awaiting guidance from Benchmark subcommittee

Need to work with the benchmarking project and define the critera

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyUSECASEUI-68

  • 0 -- none
  • 1 – baseline performance criteria identified and measured
  • 2 & 3 – performance improvement plans created & implemented
Stability01We assume that integration team will

Need to do a 72

hour ONAP soak which includes Usecase-UI

hours soak test for VF-C

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyUSECASEUI-67

  • 0 – none
  • 1 – 72 hours component level soak w/random transactions
  • 2 – 72 hours platform level soak w/random transactions
  • 3 – 6 months track record of reduced defect rate
Resiliency12automated detection and recovery

Need to work with OOM team to learn more about the mechanism they can provide.

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyUSECASEUI-72

  • 0 – none
  • 1 – manual failure and recovery (< 30 minutes)
  • 2 – automated detection and recovery (single site)
  • 3 – automated detection and recovery (geo redundancy)
Security01

increase test coverage to 50% and need help with CII badging

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyUSECASEUI-71


  • 0 – none
  • 1 – CII Passing badge + 50% Test Coverage
  • 2 – CII Silver badge; internal communication encrypted; role-based access control and authorization for all calls
  • 3 – CII Gold
Scalability001(*)

*NOTE - due to lack of resources, VF-C may not achieve level 1 for all components in this release.

and It is "Low" priority per Jason's slides from TSC 1/4/2018.

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyUSECASEUI-64

  • 0 – no ability to scale
  • 1 – single site horizontal scaling
  • 2 – geographic scaling
  • 3 – scaling across multiple ONAP instances
Manageability01support ONAP standard logging

Need to work with Logging team to identify the logging guidline.

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyUSECASEUI-65
.

  • 1 – single logging system across components; instantiation in < 1 hour
  • 2 – ability to upgrade a single component; tracing across components; externalized configuration management
Usability11

documentation is already in onap.readthedocs.io, will continue to improve

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyUSECASEUI-69

  • 1 – user guide; deployment documentation; API documentation
  • 2 – UI consistency; usability testing; tutorial documentation

API Incoming Dependencies

List the API this project is expecting from other projects.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.

Prior to the delivery date, it is a good practice to organize an API review with the API consumers.

API Name

API Description

API Definition Date

API Delivery date

API Definition link (i.e.swagger)

Portal Platform APIAPI for integration of portal applications


Catalog API (SDC)

API to read the NS and VNF Catalog




SO API(Modeling)

API for NS instantiation and termination




Micro-services bus API

API for registration and use of micro-services bus




DMaaP API

API for VNFs/VMs fcaps data subscription




A&AI API

API for gettring inventory and image management




VF-C APIAPI for NS instantiation and termination


API Outgoing Dependencies

None

Third Party Products Dependencies

None.

Testing and Integration Plans

Provide a description of the testing activities (unit test, functional test, automation,...) that will be performed by the team within the scope of this release.

Describe the plan to integrate and test the release deliverables within the overall ONAP system.
Confirm that resources have been allocated to perform such activities.

Gaps

This section is used to document a limitation on a functionality or platform support. We are currently aware of this limitation and it will be delivered in a future Release.
List identified release gaps (if any), and its impact.

Gaps identifiedImpact
To fill outTo fill out

Known Defects and Issues

Provide a link toward the list of all known project bugs.

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = usecaseui and AND issuetype = Bug AND status in (bug) "In Progress", "To Do") AND fixVersion = "Beijing Release"
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

Risks

List the risks identified for this release along with the plan to prevent the risk to occur (mitigation) and the plan of action in the case the risk would materialized (contingency).

Risk identifiedMitigation PlanContingency Plan
To fill outTo fill outTo fill out

Resources

Fill out the Resources Committed to the Release centralized page.

Release Milestone

The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.

Team Internal Milestone

This section is optional and may be used to document internal milestones within a project team or multiple project teams. For instance, in the case the team has made agreement with other team to deliver some artifacts on a certain date that are not in the release milestone, it is erecommended to provide these agreements and dates in this section.

...

DateProjectDeliverable
To fill outTo fill outTo fill out


Documentation, Training

  • Highlight the team contributions to the specific document related to he project (Config guide, installation guide...).
  • Highlight the team contributions to the overall Release Documentation and training asset
  • High level list of documentation, training and tutorials necessary to understand the release capabilities, configuration and operation.
  • Documentation includes items such as:
    • Installation instructions
    • Configuration instructions
    • Developer guide
    • End User guide
    • Admin guide
    • ...
Note
titleNote

The Documentation project will provide the Documentation Tool Chain to edit, configure, store and publish all Documentation asset.


Other Information

  • Vendor Neutral

If this project is coming from an existing proprietary codebase, ensure that all proprietary trademarks, logos, product names, etc. have been removed. All ONAP deliverables must comply with this rule and be agnostic of any proprietary symbols.

  • Free and Open Source Software

FOSS activities are critical to the delivery of the whole ONAP initiative. The information may not be fully available at Release Planning, however to avoid late refactoring, it is critical to accomplish this task as early as possible.
List all third party Free and Open Source Software used within the release and provide License type (BSD, MIT, Apache, GNU GPL,... ).
In the case non Apache License are found inform immediately the TSC and the Release Manager and document your reasoning on why you believe we can use a non Apache version 2 license.

...