BRIDGE: https://zoom.us/j/661303200

Table of Contents
maxLevel1

...

Attendance - 78%

AttendedProxy (w/ @name)Gov. HolidayDid Not Attend

Attendance is taken purely upon #info in Zoom Chat 


Time
(mins)

Agenda Items

Presented By

Presos/Notes/Links/

JIRA Tasks

1530

Release Status - El Alto

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyTSC-137
Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyTSC-137

  • OOM Branch - Is it done?
  • UUI not part of El-Alto release - Waiting for confirmation
    • Congrats to APPC, VID, MUSIC, Policy, MSB, DMaaP, ExtAPI, VNFReqs, VVP, SDNC and CCSDK -  Ready for sign-off
    • El-Alto "prototype" release - Success - lots of learning & improvements that will benefit from our incoming releases
    • No more Gerrit merge on any El-Alto branch/(master) except to fix blockers
    • OOM Branch - Is it done? AP
    • Pair-wise Testing: Modeling, OOF, ONAP CLI and Multicloud - 0: Integration Weather Board for El Alto Release
    • Too many open/in progress items in El-Alto Summary: DCAE, Holmes, OOM, Portal, SO and UUI
    • Project maturity: El-Alto Release Platform Maturity
    • Integration Status - 2: El Alto Release Integration Testing Status - Need each owner to update and estimation of remaining days ASAP thanks

    Detailed Test Status

    https://lf-onap.atlassian.net/wiki/display/DW/Integration+Meeting+Minutes

    http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-02-13.00.html

    • Security items:
      • Recent Portal SDK 2.6.0 not integrated into impacted
      compnents
      • components in El-Alto Release
    10

    Release Status - Frankfurt

    5
      • Procedure to be provided to update AAF certificates if it will expire prior May 2020 - AP VID can deliver their new certificates
      • Any other item?

    El Alto Remaining Milestones - to be adjusted due to latest Integration Lab outage

    • Completion of Integration Testing: Oct 3rd, 2019 → Oct 17th, 2019
    • El-Alto Sign-Off on Oct 10th, 2918 → Oct 24th, 2019


    15

    RelEng/Infrastructure

    ESCALATION concerning our ONAP Infrastructure Improvements (CI/CD & Testing)

    wikionaporg71827884
    • 16393187
    • Account has been created but still required
      • credentials to automate deployment and removal.

      • Enable the registration of an application (in Azure Active Directory) in order to be able to deploy Azure Kubernetes service.

    ------------------------------------------------------------------

    Review previous action items - AP

    ------------------------------------------------------------------


    15

    Subcommittee Update

    Security

    • SECCOM update: what shall we do with the projects not taking any effort on developing security best practices -
    example of MSB?
    30

    Release Status - Frankfurt

    • PTL requested on 9/30 to create M1 JIRA Release Management Tickets
    • Frankfurt scope is now frozen - v95
    • Kick-Off Prioritization - First Feedback
      • Project Impacts should be filled in
      • Review of XL, L - multiple releases?
      • Company's engagement includes
        • Ownership till the release sign-off
        • Developers and Testers
        • Automated Test cases for any requirement is a must
        • Bug fixing, Security/License issues
      • Any Use Case/Requirement should be reviewed - GO/NO GO from Architecture - ONAP Frankfurt Release Architecture Requirements
      • Alla also provided on behalf of Use Case Sub - some recommendations - see TSC e-mail
      • Backlog of S3P requirements to be considered - common to ONAP projects  - AP (Jason/SECCOM/Archi)
        • Upgrade component
        • Storage Classes
        • Geo-redundancy
        • oParent Integration
      • Upgrade to Python 3.0; Java 11.0 - next 2 releases goal?
      • Documentation

    Image Added


    10

    TSC Activities and Deadlines

    #1Review #1 Review ONAP Release Cadence

    • Task force driven by Chaker Al-Hakim
    • Target Implementation: GulinGuilin
    • Initial Inputs:
      Jira Legacy
      serverSystem Jira
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
      keyTSC-20

    #2 Finalize Project Life cycle - Chaker Al-Hakim

    #3 Review ONAP Marketing Messaging - cl664y@att.com

    Jira Legacy
    serverSystem Jira
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyTSC-137

    5

    Incoming Events

    • ONAP/CNTT F2F Event in January 1314-16th, 2020 - Budapest (TBC)
    • ONAP event before or after ONS North America - Los Angeles (TBC)
    • ONAP event before or after ONS North Europe - Antwep (TBC)
    • TSC Election as soon as TSC agrees on the next TSC composition


    Action Items

    •   From 10/7/2019 - Jim/David to add 15 mins slot to PTL agenda to review/discuss TSC-137
    •  10/7/2019 - Pawel/David to discuss about Portal SDK 2.6.0 integration plan post El-Alto

    ...

    •  10/3 - Jim will create M1 Frankfurt JIRA Release Management