Agenda
- Status and Stucks
- Technical Discussion
- Making the PTL Happy
...
- Status and Stucks
Current POMBA Dublin Stories (Logging Project) -
Current Code Inspections
- POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
- General Status
- Casablanca (Maintenance)
- Tasks to be closed off (just a technicality):
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-456 - Move to Dublin since this is where the work was actually done
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-470 - Move to Dublin since this is where the work was actually done
- Tasks to be closed off (just a technicality):
- Dublin
- Stories in progress:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-768 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-765 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-762
- Stories to be formally verified before closure:
Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-764 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-779 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-404
- Bugs to enter:
- Latest security scan results show ~9 medium issues that should be recorded (but aren't severe enough to merit immediate work).
- Bugs entered in last week:
- N/A
- Bugs in progress:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-852
(Verify in OOM fails, assigned back to design)Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-803 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-916
(high)Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-917
- Bugs to be verified:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-807 Jira Legacy server System Jira columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-808 Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-857 - Need to ping Sylvain. (Catherine pinged last week.)
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-875
- Bugs closed off since last meeting:
Jira Legacy server System Jira serverId 4733707d-2057-3a0f-ae5e-4fd8aff50176 key LOG-909
- Stories in progress:
- Casablanca (Maintenance)
- Technical Discussion
- Note OOM changes should be done when manifest changes are done. Should not wait for integration team to do this work for us.
- Did we miss these in Casablanca?
- Pomba data router missed this yes, resulting in a last minute change
- Gary from Integration had to do it.
- Pomba data router missed this yes, resulting in a last minute change
- We will have to do this for Dublin in two months.
- Create task to track J. Ram Balasubramanian
- Did we miss these in Casablanca?
- Organizing Models and Swaggers between releases
- Basic navigation should take us to current
- It should also be possible to get Casablanca information
- Wiki needs some reorganization
- Integration Team discussion
- When we know the Openstack/network discovery info will work in ONAP, we shall reach out to Brian and the Integration team again.
- Logs now fixed, finding some additional bugs, but now easier to address. When resolved, can communicate.
- Logs now fixed, finding some additional bugs, but now easier to address. When resolved, can communicate.
- How to test L2 Fabric
- Some of that information may be not be available in ONAP
- But the resources will be, even if for other reason.
- When we know the Openstack/network discovery info will work in ONAP, we shall reach out to Brian and the Integration team again.
- Consider demo schedules
- J. Ram Balasubramanian will forecast demos as development progresses
- Data Dictionary & Network Discovery- Dec 20
- Done
- L2 Network data - beginning of Feb?
- Set a more specific date in January
- Network Audit and/or additional enhancement - end of Feb/mid March?
- Data Dictionary & Network Discovery- Dec 20
- J. Ram Balasubramanian will forecast demos as development progresses
- Note OOM changes should be done when manifest changes are done. Should not wait for integration team to do this work for us.
- Making the PTL Happy
- ONAP Casablanca Maintenance? Michael O'Brien as of now Logging and Pomba are not in 3.0.1-ONAP - only critical fixes should go in if we have any
- Consider porting bugs into maintenance (add label for candidates)
- Only high and highest ones. Ones that impact other components, prevent POMBA from launching or the audit to even start.
- Note the following date to submit bug fixes into Casablanca - Dec 10 (M1), Jan 10 (Docker Release Image), Jan 24 (Release Notes)
- Supposed to go out today, but Michael doesn't think we are not ready. There are 5 OOM patches, including one for POMBA.
- ensure you paste results of a CD deploy when creating code inspection. Don't rely on integration team.
- cube CTL
- health check
- get pods
- ensure you paste results of a CD deploy when creating code inspection. Don't rely on integration team.
- Consider porting bugs into maintenance (add label for candidates)
- Ensure that the ONAP wiki is complete and accurate for deployment instructions
- undercloud instructions for the cluster
- Dublin
- Should look at milestones and ensure we are in good shape.
- Feature commitment Jan 17 → pushed one week. Jan 24th.
- Prudence is supporting Michael for this activity.
- Functionality freeze Feb 14
- API freeze is March 14th.
- Feature commitment Jan 17 → pushed one week. Jan 24th.
- Should look at milestones and ensure we are in good shape.
- ONAP Casablanca Maintenance? Michael O'Brien as of now Logging and Pomba are not in 3.0.1-ONAP - only critical fixes should go in if we have any