Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: add status for VID

Table of Contents

...


ProjectPTL

Release Planning Artifacts

Release Planning ChecklistTime UTCTSC Disposition
1Virtual Function ControllerYan YangRelease PlanningChecklist14:05

Review approved w/ contingencies-

1) trim down the committer list.

2) arch subcommittee decision on SO next week.

2HolmesGuangrong FuRelease PlanningChecklist14:12Review approved w/ contingency PTL for holmes, dcae, clamp & policy provide recommendation to TSC next week .
3CLAMPGervais-Martial NguekoRelease PlanningChecklist14:19Review approved
4Microservices BusHuabing ZhaoRelease PlanningChecklist14:26Review approved w/ contingency - trim down the committer list
5CLIKanagaraj ManickamRelease PlanningChecklist14:33-- not reviewed --
6Usecase UIShen TaoRelease PlanningChecklist14:40

Review approved w/ contingency - complete the checklist

7Software Defined Network ControllerDan TimoneyRelease PlanningChecklist14:47

Review approved w/ contingency- discussions over VoLTE usecase requirements with SDN-C

8Policy FrameworkPamela DragoshRelease PlanningChecklist14:54

Review approved

9Portal FrameworkLeimeng Shi (backing ip Manoop Talasila)Release PlanningChecklist15:01

Review approved w/ contingencies-

1) upload image file to the wiki -assistance needed

2) solicit additional community participation

10VNF-SDKChristopher DonleyRelease PlanningChecklist15:08Review approved
11

Data Collection, Analytics, and Events

Vijay V Kumar (backing up Lusheng Ji)

Release PlanningChecklist15:15

Review approved w/ contingencies-

1) move VESCollector from incoming to outgoing API dependencies

2) clean-up contributor list- too many blanks

12VNF Validation ProgramErik SundelofRelease PlanningChecklist15:22Review approved
13Active and Available Inventory Jimmy ForsythRelease PlanningChecklist15:29Review approved
14Application ControllerRanda MaherRelease PlanningChecklist15:36

Review approved w/ contingencies-

1) in/out API section needs to be updated based upon information previously discussed in this session - review next Friday

2) checklist to be completed

15ModelingHui DengRelease PlanningChecklist15:43-- not reviewed --
16



15:50

...


ProjectPTLRelease Planning ArtifactsRelease Planning ChecklistTime UTCTSC Disposition
1ModelingHui DengRelease PlanningChecklist14:05Review approved w/ contingency resource allocation updates
2Service OrchestratorSeshu KumarRelease PlanningChecklist14:12Review approved w/ contingency resource allocation updates
3Multi VIM/CloudXinhui LiRelease PlanningChecklist14:19Review approved w/ contingency on resource allocation and action of risk section
4VNF RequirementsSteven Wright Release PlanningChecklist14:26-- not reviewed --
5CLIKanagaraj ManickamRelease PlanningChecklist14:33Review Approved
6Integration
Helen ChenRelease PlanningChecklist14:40Review Approved
7CCSDKDan TimoneyRelease PlanningChecklist 14:47Review Approved
8DMAAPRam KoyaRelease PlanningChecklist14:54

-- not reviewed – move to tsc meeting


9DocumentationRich BennettRelease PlanningChecklist15:01Review Approved
10External API FrameworkAndy MayerRelease PlanningChecklist15:08Review approved
11ONAP Operation ManagerDavid SauvageauRelease PlanningChecklist15:15

Review Approved w/ contingency on resource allocation and checklist


12Optimization FrameworkSarat PuthenpuraProject planned for Beijing Release. No need to be reviewed.15:22

-- Beijing release, not Amsterdam --


13Review of June 30, action items


15:29
14Network Function Change Management project proposalEmmanouil Mavrogiorgis

15:45Will be handled either as a subcommittee otr a use case for the Beijing release. Proposal is withdrawn.


Review Thursday, July 13


ProjectPTLRelease Planning ArtifactsRelease Planning ChecklistTime UTCTSC Disposition
1Virtual Infrastructure DeploymentAmichai HemliRelease PlanningChecklist14:05

Project artifacts not complete. Required work. Catherine will lead the effort. Next review scheduled in July 20.

Project reviewed and approved by TSC on July 20.

2Service Design & Creation
Eden Rozin (backing up Michael Lando)Release PlanningChecklist14:12

Approved with following to work on:

  • Add Architecture, API dependencies, scope and MVP.
  • Team to discuss the "no" item in the checklist.
3Logging EnhancementsLuke Parker (backing up Mark Pond)Release PlanningChecklist14:19

Approved

  • PTL to balance resource list
  • Provide an example of how project could use the log mechanism.
4Application Authorization FrameworkRam KoyaRelease Planning
?
Checklist14:26

Approved

  • PTL to evangelize his project to ensure adoption within ONAP community.
  • PTL to balance resource list
5DMAAPRam KoyaRelease PlanningChecklist14:33

Approved with following to work on:

  • PTL to balance resource list
6VNF RequirementsSteven Wright Release PlanningChecklist14:40
7

Approved with following to work on:

  • Fill out deliverables section
  • Integration plan requires clarification with Integration Team (Helen Chen)


F7University
Mazin Gilbert/
Nermin Mohamed
Update
Decision to update the community
on latest discussions/decisions
after meeting with LF on July 14.

14:47