The page is intended to summarize all the requirements for Dublin Release.
...
The Release Scope was finalized during the M1 Release Planning milestone at the TSC on January 31st.
The Requirements extracted from SP lists of priorities for Dublin are covered either by the Use Case, the functional requirements, the non functional requirement or within a project scope of work.
...
- Green: The functional requirement will be fully implemented and tested
- Yellow: The functional requirement will be partially implemented. It is possible to identify capabilities for this functional requirement that can be tested (phasing approach).
- Red: The functional requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
...
M3 checklist for Consistent ID of a Cloud Region
...
APPC(TO, code already exists),
SDN-C: test support only
...
SO: Support testing effort, changes are likely in.
VFC:Committed
UUI:Committed
VID: Committed based on ATT resources
...
AT&T
China Mobile
...
Status | ||
---|---|---|
|
...
Y
...
...
Pending code review and integration
<please provide gerrits awaiting review>
...
AAI: TO
SO: Code Hardening, Expansion of use-case support, testing
...
Intel
ARM(???)
...
Status | ||
---|---|---|
|
...
Status | ||
---|---|---|
|
...
Status | ||||
---|---|---|---|---|
|
...
CLAMP: Committed (Based on TechM resource commitment)
Policy: Committed (Based on TechM Resource Commitment)
...
Status | ||
---|---|---|
|
...
Y
Status | ||
---|---|---|
|
M3 Gate for "K8S based Cloud Region Support"
...
Status | ||||
---|---|---|---|---|
|
Code delivered in SDC, SO and MultiCloud. Pending Integration.
...
...
SDC & SO: Committed based on Intel/VMWare contribution
AAI: Partially committed
...
AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability
...
SO (AT&T) and VID
(Nokia) Testing confirmed by CM Team (AT&T)
...
Y
...
VID functionality completed; SO blocked by SDC issue in deploying workflow into SO
<if feature not complete already - move to OUTPLAN>
...
...
SO (C),
VID (C)
...
SO: Committed (AT&T)
VID: pending final decision from Nokia (stretch goal)
...
AT&T
Nokia
2
...
Status | ||
---|---|---|
|
Testing confirmed by Orange and AT&T
...
APPC Dublin M3 Deliverables for API Freeze Milestone Checklist Template
...
Functionality completed; Working on code coverage; code is yet to be merged;The portion of code in APPC has been merged.
<if feature not complete already - move to OUTPLAN>
...
...
APPC (C),
OOF (C),
A&AI (TO)
...
APPC: Committed (Orange)
OOF: Committed (Orange)
...
Orange
...
Status | ||
---|---|---|
|
Testing confirmed by AT&T
...
...
Feature completed; working on code coverage
...
...
OOF (C),
Policy (TO)
...
Status | ||
---|---|---|
|
Testing confirmed by AT&T
...
Y
...
Status | ||
---|---|---|
|
...
Status | ||||
---|---|---|---|---|
|
...
...
Model driven Control Loop Design
...
DCAE: AT&T Committed
CLAMP: Committed
Policy: Committed
...
AT&T commits to finding the required resources
...
SO Only
Testing confirmed by SO Team
Y
...
...
SO, SDC, VFC, APPC, SDNC
https://jira.onap.org/browse/CCSDK-575
...
SDC: Not committed
APPC: Not committed
SO: Committed based on the code from R3
SDNC: Not committed
VFC: Partially committed
...
SDC: no resources, not enough info
APPC: no resources
SDNC: no resources
VFC: optimize DB microservice
CDS project will provide Resource assignment functionality
...
ETSI Alignment
SOOL003 plug-in to SO
Ericsson confirmed the integration testing resource for the ETSI SOL003-plugin support
...
Y
...
Status | ||||
---|---|---|---|---|
|
Code delivered in SO and A&AI; working on VNFM Simulator for integration testing
...
ETSI Alignment
SO plugin to support SOL003 to connect to an external VNFM
...
...
SDC: Partially committed (based on Ericsson contribution)
SO: Committed (SOL003) based on contribution from Nokia and Ericsson
AAI: Not Committed
SDC: no resources
.AAI: no resources (detailed impact to be discussed) Action Byuong
...
Architecture did not approve
...
...
...
...
Prabhu Balan – (prabhu.balan1@vodafone.com) from Vodafone.
...
...
Y
...
...
SDC
CLI/VNFSDK
...
Vodafone, iconectiv, huawei
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
...
- Green: The non-functional requirement will be fully implemented and tested
- Yellow: The non-functional requirement will be partially implemented. It is possible to identify capabilities for this non-functional requirement can be tested (phasing approach).
- Red: The non-functional requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
...
TSC M1
Approval
...
...
...
...
- Support TOSCA network constructs
- Single click instantiation (Using VID)
Y
...
Status | ||
---|---|---|
|
...
Status | ||
---|---|---|
|
End 2 End tests to start
...
...
SO
SDC
CCSDK
OOM
Testsuite
Documentation
...
Jira Legacy | ||||||||
---|---|---|---|---|---|---|---|---|
|
https://wiki.onap.org/download/attachments/48529726/ONAP-E2E-Automation-v3.pptx?api=v2
...
Code:
SO
SDC
CCSDK
OOM
Testsuite
APPC (CDS)
TO:
AAI
DMaaP
Policy
SDC:
TechM (C)
IBM (C)
CCSDK:
ATT (C)
Bell (C)
IBM (C)
Ericsson (C)
TechM (C)
SO:
Ericsson (C)
Bell (C)
ATT (P)
OOM:
Orange (P)
Bell (C)
...
T
...
Documentation:
Orange (C)
Bell (C)
Dutch T (C)
AAI: TO
...
AT&T
Bell Canada
Ericsson
Huawei
IBM
Orange
Tech Mahindra
...
Container optimization : on –going (eg SDNC)
Testing Strategy
https://lists.onap.org/g/onap-tsc/message/4605
...
Status | ||
---|---|---|
|
Reduction effort between Casablanca and Dublin
Some old images to be renewed
CIA team will endorse SDC
Optimized Docker excpected to be ready for RC0
...
Status | ||
---|---|---|
|
...
S3P - Footprint Optimization (Integration with Alpine)
Alpine is the target, but possibility to use oother based OS (cf TSC 2019-02-28)
...
...
-
...
Documentation by PTL no more useful: the wiki page will provide weekly information:
Effort also required to avoid old images, cf JIRA tickets
Jira Legacy | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|
...
SDC: N
CCSDK, CLAMP: Committed
Multi-VIM/loud: committed
Policy: committed
DCAE: Not committed
SDC: no resources
DCAE: Resource constraint
...
Orange
OAM
Amdocs
+ PTL
...
Component/memory optimization: Ongoing Assessment
Testing Strategy
https://lists.onap.org/g/onap-tsc/message/4605
...
Global effort to optimize resources for small installation
Capabilities to configure JAVA_OPTS for Java based images
...
Status | ||
---|---|---|
|
The ONAP Minimal Deployment target OK.
Some attention required for AAI
...
...
Checklist and wiki to be published.
...
SDC: N
CCSDK, CLAMP: Committed
Multi-VIM/loud: committed
Policy: committed
DCAE: Not committed
SDC: no resources
DCAE: Resource constraint
...
Orange
OAM
Amdocs
...
Global optimization (e.g. shared DB) - stretch goal=shared PostgreSQL; shared MariaDB
Testing Strategy
https://lists.onap.org/g/onap-tsc/message/4605
...
Shared DB instance creation on-going
First integration with ONAP component on-going
...
Status | ||||
---|---|---|---|---|
|
Code OK for Mariadb-galera cluster and Cassandra cluster
A&AI Integrated with Shared Cassandra. SDC has been tested but in discussion with PTL on merging into release.
SDNC and SO (in test - awaiting PTL approval) with mariadb-galera.
...
...
First component using Shared DB: AAI using Cassandra
List of JIRA tickets
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
...
SDC: N
CCSDK, CLAMP: Committed
Multi-VIM/loud: committed
Policy: committed
DCAE: Not committed
SDC: no resources
DCAE: Resource constraint
...
Yes with limited scope: Manual PH1
...
Healthcheck gate is operational
...
Status | ||
---|---|---|
|
Infrastructure up , per commit triage working well- thank you Orange
...
TSC Task Force:
OOM + Integration
(Infrastructure)
Jira Legacy | ||||||||
---|---|---|---|---|---|---|---|---|
|
...
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
...
Integration
Logging
OOM
+ ALL (helm charts)
...
no except devops/scripts
in
oom/integration
...
OOM:
Linux Foundation (C)
Orange (C)
Bell (C)
Amdocs (C)
Logging:
Bell (C)
Amdocs (C)
Integration:
...
Amdocs
Orange
Linux Foundation
Bell
Huawei
...
Status | ||
---|---|---|
|
...
...
Status | ||
---|---|---|
|
Security Checklists integrated to the Release Milestone templates
Yes
...
Status | ||||
---|---|---|---|---|
|
Yellow
- Vulnerability Review Tables not complete for some projects
- Some projects missing answers for CII Passing badge
...
...
De-scoped from Dublin - TSC decision on 2/21
...
Status | ||
---|---|---|
|
...
Status | ||
---|---|---|
|
In progress:
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
...
Transfer for A&AI targeted for April 18th,2019. Once successful, will transfer:
- policy
- aaa
- appc
- dcae (awaiting review of documented process before proceeding - see below)
OOM - Development workflow after code transfer to tech teams
...
...
No enforcement to make it happen for all project in Dublin release, but expectation to to completed within El Alto release. This could potentially be a S3P items.
...
Status | ||
---|---|---|
|
...
Security Subcommittee
...
AAI, DCAE, DMaaP, Holmes, Logging, Modeling, MSB, Multi-Cloud, ONAP CLI, UUI, Policy, Portal, SO, VFC, VNFSDK, AAF,CLAMP, MUSIC: Already Integrated
ExtApi, VID: Committed
SDC: Not Committed
CCSDK/SDNC, OOM, APPC, OOM: No
CCSDK/SDNC, APPC: dependency on ODL
OOF (HAS, OSDF): python, not Java
SDC: No resource
OOM: No java code
...
Reviewed on 2/14 with the Integration Team
Final presentation to the PTLs on 2/19
Yes
...
Some teams raising requests/risks to get help achieving this by M4.
...
Status | ||||
---|---|---|---|---|
|
Lack of people
See Risks
...
Integration Team
...
View file | ||||
---|---|---|---|---|
|
...
See Dublin Release Platform Maturity
...
OOF is running in multiple geos. Portal also using MUSIC. SDC & Policy will be in next release.
...
...
OOM (introduction of CNI)/MUSIC capabilities leveraged by initial ONAP Components i.e. OOF, Portal, SDC
...
Status | ||
---|---|---|
|
...
Yes
...
Jira Legacy | ||||||||
---|---|---|---|---|---|---|---|---|
|
...
Jira Legacy | ||||||||
---|---|---|---|---|---|---|---|---|
|
...
Testing confirmed by Nokia - Przybysz, Marcin
...
Yes
...
ONLY DCAE component. No other projects securing the xNF comms.
...
xNF communication security enhancements.
...
...
Slide presented on PTL Call (1/14/2019)
DCAEGEN2-1101 - DCAE enhancements to support certificate authentication for HTTPS. All HTTPS connections from xNFs go to DCAE so no other projects need to be updated.
DCAEGEN2-978 - DCAE replaces clear text password with hash.
DCAE - Committed based on Nokia's contribution
...
see yellow/red in
in progress
log, aaf cli, consul, contrib, dcae, dmaap, nbi, oof, sdnc, so, uui, vid, vnfsdk, vvp
good
aai, appc, clamp, esr, multicloud, policy, pomba, portal, sdc, vfc
...
Library: In progress portal/sdk and possible so library adjustment
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
Infrastructure: dmaap is adding containers, need to work with other teams in red
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
as part of overall
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
...
Log
OOM
Portal
SO
AAI
...
OOM (c)
LOG (c)
Portal (c)
SO (c)
AAI (c)
Multicloud(c)
LOG/POMBA
OOM
Amdocs
AT&T
Bell
Hauwei
Intel
...
No particular Integration Testing required.
Portal/UUI Teams will provide the testing resources
...
Implementation complete - test phase
...
...
Code:
PORTAL, UsecaseUI
...
Development Stretch Goal for Dublin. No particular Integration Testing required. Portal container at RC0 will be the final version to be tested
...
Implementation and documentation of the Angular upgrade that is scoped in Dublin is complete. Further, new screen changes are being planned to E release (as the Angular upgrade is a huge XL sized effort)
...
...
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
Jira Legacy | ||||||
---|---|---|---|---|---|---|
|
...
Code:
PORTAL
TO:
Policy, VID
...
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
...
POC Definition - (In Progress)
...
Self Serve Control Loop (Closed Loop Subcommittee)
...
...
Model driven Control Loop Design
This is a stretch goal for Dublin. We are still trying to align resources so that this can be accomplished this release
...
DCAE: Stretch Goal
Policy: Stretch Goal
SDC: Stretch Goal
...
Status | ||||
---|---|---|---|---|
|
Due to Resource Constraint this will be pushed to the next feature release
...
...
OOF: Committed
MultiVIM/Cloud: Committed
End-to-end Use Case Integration: Stretch Goal (due to several workflow changes)
IBM, AT&T, VMware (Architecture/Modelling), Intel (Architecture),
...
...
...
Status | ||||
---|---|---|---|---|
|
Software is still under development.
...
CI/CD
Magic word "run-helm-deploy" in queue at LF, Orange and Log team
Move to POC
...
TSC Task Force:
OOM + Integration
(Infrastructure)
...
Amdocs
Orange
Linux Foundation
Bell
Huawei
...
...
-Healthcheck
-vFW
...
Progress stalled - Global - jjb is a higher priority.
...
SO plugin to support SOL005 to connect to an external NFVO
...
...
https://wiki.onap.org/pages/viewpage.action?pageId=58229331
Functional Requirements
...
Distributed Analytics as a Service (Dublin Summary) - Edge Automation
...
Demo
...
Day-2 Config and Visualization package is pending.
...
S3P - Provide Upgrade Capabilities PH1
...
...
OOM supported by A&AI, SO, SDC and SDNCWaiting for inputs
...