The ONAP community chose to re-name the "K" release (originally "Kyoto") in honor of the late CNCF Executive Director, visionary, entrepreneur, and open source advocate and pioneer, Dan Kohn, who passed in the fall of 2020.  More information about Dan here.

Release Schedule

Revision:  r1 proposal (not yet approved)Image Removed r10

Image Added

Activity Log

DateRevEvent or UpdateMilestones Affected
11/10/22r10The TSC agreed that the release was not ready for Sign Off.  The Sign Off date was pushed out 3 weeks to account for ONE Summit next week, and Thanksgiving the week after.Sign Off
10/27/22r9The TSC conditionally approved RC for Oct 28 (+1 day from scheduled). See meeting notes for details. No change to Sign Off.RC
10/06/22r8The TSC conditionally approved Kohn release M4. The condition was that the projects complete the three unresolved release management tasks (INT-2145, INT-2146, & OPTFRA-1093) by the RC milestone.M4
10/03/22r8The issues with the build environment remain unresolved.  The PTLs agreed to re-schedule M4 for Oct 6.M4
09/29/22
Due to ongoing issues with the build environment (IT-24608, it-24620), the TSC agreed to re-examine the status of M4 at the PTL meeting on Oct 3.M4
09/22/22r7

The TSC approved M3

The TSC agreed to push out M4 and RC by one week, each.  Sign off is unchanged.

M3, M4, RC
09/14/22r6It appears that there was a misunderstanding about M3 on Sept 1.  The TSC chair tells me that the intention was actually to move both M3 and M4 to the same date on Sept 22.  Schedule is updated to reflect that.M3
09/01/22r5

The TSC pushed M3 and M4 out by one week, each to Sept 8 and Sept 22, respectively. Other milestones remain the same.

Also added the Thanksgiving holiday.

M3, M4
07/21/22r4The TSC conditionally approved M2.M2
07/14/22r4

The TSC pushed M2 out one week to July 21.

Also updated the sign off date shown for the Jakarta release to the actual release date (June 30).

M2
06/23/22r3The TSC conditionally approved M1M1
06/09/22r3The TSC approved moving M1 to June 23.M1
06/02/22r2The TSC approved moving M1 to June 9 (May 24 proposal)M1
05/24/22r2Updated May 19 proposal based on feedback from PTLs at May 23 PTL meeting. Moved M2 from June 30 to July 14. Still requires TSC approval.M2
05/19/22r1

Identified a conflict between M1 and Ascension Day on May 26, due to Ascension Day not being on the original schedule.  Proposed moving M1 to June 9 and M2 to June 30.  Need to review with PTLs and then vote in TSC on June 2.

Added Ascension Day.

M1, M2
03/31/22initial approvedTSC approved Kohn scheduleAll
03/10/22
First draft postedAll

...