Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...


DescriptionDocumented byComments / Follow-up
1

Simplify documentation tracking table

Planned for Istanbul
2

Track repositories not documents in the document tracking table

Planned for Istanbul
3Create separation between completion of code reviews and container delivery by adding another milestonePlanned M3 tasks moved to M4.  Need to discuss tasks for M3.  Planned for Istanbul
4Reconsider time between RCs.  One week seems too tight.Only plan a single RC, beginning with Istanbul
5Reconsider RCs altogether.  What do they contribute? Are they necessary? (Kenny)Only plan a single RC, beginning with Istanbul
6Better tracking of OOM / integration status.   Gerrit filter that Krzysztof created was helpful.Needs more discussion.  Possible for Istanbul.
7xtesting dockers (tests) and xtesting-onap (test launchers) should have been frozen before RC0..so next time we have to think to that..Integration shall guarantee a stable testing baseline to OOM to gate confortably. (Morgan https://lists.onap.org/g/onap-tsc/message/7653)Needs more discussion.  Possible for Istanbul.
8Create JIRA Management Tasks for Sign-Off (OOM, Integration and Doc)?cl664y@att.comNeeds more discussion.  Possible for Istanbul.
9Strong pushback on Project Patch Acceptance page.  Confusing? Redundant? Should we remove.David McBrideRemoved for Istanbul.
10Requirements should be completed on time.  Need more schedule discipline.  Milestones missed should defer requirements to next release.
11Need a better defined schedule for maintenance releases.

David McBride :  should define a process before we define a schedule.