Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Page Properties


Name
Milestone or Requirements Exception?Milestone

Project or Requirement Name and JIRA

Policy

Milestones affected

RC0

Projects affected

Policy

Background descriptionOOM review of Policy for M3 is still not merged.  M3 review finally merged.  Review for RC0 will not begin until 3/10.  Given the time it takes to run oom_deploy, it is unlikely to complete before RC0.
Schedule impact

This will continue to delay RCn milestones with respect to Policy, RC0 in particular

Recovery plan

Update OOM review to latest Policy images

Milestone schedule change


Risk

Review may continue to fail to build.  Obtain a waiver

StatusClosed
DecisionWithdrawn