Default
- All high/highest priority jira tickets addressed
- Remaining License scan, security critical issues addressed
- Update Release note and documentation
- Docker images “Release” dues
- Project specific test plan for El Alto completed
- Update Frankfurt Risks
- Integration Weather Board complete
- Versioning at the project level
- Check the certification expiry of your application. It should be valid for the next 9 months after RC0.
Proposal
RC is the milestone where integration starts working on the release candidate...
General
- All high/highest priority jira tickets addressed
- Update Release note and documentation
- Update Frankfurt Risks
- Versioning at the project level
Use cases
- Project specific test plan for Frankfurt initiated (due docker needed to build the target env)
- Documentation completed
- Integration Weather Board complete
Labs
- the integration labs shall be Frankfurt ready, installed with the due dockers at RC
CI/CD
Daily Frankfurt created and running on 2 labs
- Frankfurt CI/CD chain successfull (all tests OK)
Tests
- Preparation of Robot and testsuite docker provided dockers (but due dockers needed as prerequisite + time to complete integration)