Julia Li
Joanne Liu-Rudel
Kingsly
- RaZwYjP4nmBlczY43F4p1ssq
- Shankaranarayanan Puzhavakath Narayanan
- Carlos Andrade
- Devendra Chauhan
- Melanie Sater
Agenda
- M4 status and pending items
- Winlab status - availability and fallback plan
- Testing
- RAN topology file
- El Alto updates
M4 Scorecard as of 4/11:
YELLOW
Use case is feature complete and code committed.
Code delivered for DCAE and Policy.
For SDN-C, code delivered for 2 items. SDNC-431,433 moved to El Alto. SDNC-431 code complete but not merged.
For OOF code committed, and needs to be merged.
SDNC-431 - Implement config DB and REST API (SDN-R / OOF interface)IN PROGRESS
SDNC-433 - Receive netconf notification from RAN, update configDB, and publish change on DMaaP OPEN
Plan: Add note that
Winlab Status / Testing: Work is still ongoing. At this point, we do not have an estimate of when the new environment will be available.
There is a risk that integration testing timeline is affected, even if things are ready for the POC in June.
N.K. Shankaranarayanan to follow up and confirm what is available before next week call. Will need to raise issue with Integration team re. backup plan of using WIndriver lab if needed.
El Alto / Frankfurt Release:
Reviewed 5G Use Case updated wiki page. We are assuming that, as per recommendation, El Alto release will be a maintenance release.
For OOF-SON use case, El Alto will essentially contain code from the use case, including carryover items from Dublin.
New features and RAN-Sim proposed for El Alto will be targeted for Frankfurt release (release date expected around Feb 2019).
Frankfurt release planning expected to be concurrent with El Alto.
RAN Topology file:
Need to modify topology file so that RAN SimGUI views shows neighbors clearly for POC demo.