The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.

M3 Release Architecture Milestone overview is available in wiki.

Arch review 20180814 - editing this page this week

...

Provide Link to Project backlog
Practice AreaCheckpointYes/NoEvidencesHow to?
Architecture


Has the Project team reviewed the APIs with the Architecture Committee (ARC)?Yes

20180814

Logging Casablanca M3 Architecture Review

Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough.

Is there a plan to address the findings the API review?Yes

Adjust Logging Casablanca Scope

and Logging Dublin Scope


The plan could be as simple as a Jira issue to track the implementation of findings or a documented plan within the wiki.
Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval?YesNA
In the case some changes are necessary, bring the request to the TSC for review and approval.

Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone?

No

If Yes, please a link to the evidence of these changes.

see spec page started in beijing

ONAP Application Logging Specification v1.2 (Casablanca)

Critical point to understand is that change is inevitable, and that right timing and clear communication to the community will ease the process of accepting changes.
Provide link to the API Documentation.
ONAP Application Logging Specification v1.2 (Casablanca)
Release ManagementAre committed Sprint Backlog Stories been marked as "Done" in Jira board?Yes

https://jira.onap.org/secure/RapidBoard.jspa?rapidView=143&view=planning.nodetail&epics=visible


query

project = LOG AND status in (Open, "In Progress", REOPENED) AND (labels not in ("POMBA") or labels is EMPTY)

Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira?Yeshttps://jira.onap.org/secure/RapidBoard.jspa?rapidView=143&view=planning.nodetail&epics=visible
Have all findings from previous milestones been addressed?Yes

Provide link to JIRA findings

Logging Casablanca Scope

and addressed logging resource issues in Casablanca Risks


DevelopmentHas the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)Yes

Goal: 50% for Incubation project in Beijing

we have 88.8

https://sonar.onap.org/dashboard?id=org.onap.logging-analytics%3Alogging-analytics

Guidance on Code Coverage and Static Code Analysis

Tools: Sonar

Is there any pending commit request older than 36 Business hours in Gerrit?Nohttps://gerrit.onap.org/r/#/q/status:open+project:+logging-analytics

Do you have a plan to address by M4 the Critical  vulnerabilities in the third party libraries used within your project?

Yes

Jira Legacy
serverSystem Jira
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyLOG-604

Ensure by M4 the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo.

There are license issues with the IQ server as of 20180820: https://lists.onap.org/g/onap-discuss/topic/clm_cve_links_from_jenkins/24819369?p=,,,20,0,0,0::recentpostdate%2Fsticky,,,20,2,0,24819369

Are all the Jenkins jobs successfully passed ( Merge-Jobs)?Yes

first 5 jobs are for logging

https://jenkins.onap.org/view/logging-analytics/


Are all binaries available in Nexus?yes

2 libraries in nexus.onap.org

details in Logging Developer Guide#pom.xml

https://nexus.onap.org/service/local/repositories/snapshots/content/org/onap/logging-analytics/logging-slf4j/

https://nexus.onap.org/service/local/repositories/snapshots/content/org/onap/logging-analytics/logging-library/


Integration and Testing

Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins?

N/A

Provide link to evidence

in progress

Jira Legacy
serverSystem Jira
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyLOG-245


Has the project code successfully passed the Daily Build process?Yes

Goal is to ensure the latest project commit has not broken the Integration Daily Build 

https://jenkins.onap.org/view/integration/