Agenda:
- Review status on items assigned to dev team
- Go over JIRA list assigned for Beijing release
- Discuss M1 planning and check list for Beijing release
...
Chris Lott, Giri, Weiting, Leimeng Shi, Sunder Tattavarada, BINDU ELISETTY, HIMA (hbindu@research.att.com), Farhan Mir
Discussion Items:
- Who is the replacement for testing lead? - Leimeng to followup
- Portal-151 - followup with usecaseui and schedule a session to review the architecture - Leimeng
- Portal-182 - CLI integration help - Leimeng to setup a working session - Sunder Tattavarada/Former user (Deleted)
- Portal-155 - security issues scan - Farhan/Sunder
- Plan to release SDK 2.1.0 version and then communicate to partners to update their poms - Sunder/Leimeng - ETA 1/17.
- Extend Portal-119 to split DB for Portal and SDK - Robert - provide ETA by 1/11
- Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - done - Hima will be cleaning up - ETA 1/10.
- SDK will be next to scan - Lorraine - ETA 1/11
- Split Portal-19 to Hima and Robert (based on Lorraine's scan output) - create tasks based on the scan - Robert to analyze the font "Omnes-ECOMP-W02".
- JUnit /Sonar coverage to 50% on SDK and Portal. (
- SDK - JUnit test coverage from 4% to 50% - Hima (pending code review and push to gerrit)
- Portal - target 30% to 50% - Giri (to coordinate with Hima to find the right code modules)
- Discussed remaining JIRA items in great details
- M1 due on 1/818/2018 (same template as Amsterdam) - Manoop/Leimeng
- Check with IBM team members - Manoop/Abbas/Sunder
- Beijing Release Planning:
- M0 - dev kick-off, Nov 16
- M1 - planning Jan 16
- M2 - functionality freeze Feb 15
- M3 - API freeze Mar 1
- M4 - code freeze Apr 5
...