The following items are expected to be completed for the project to Pass Release Sign-Off Milestone.
Release Sign-Off Milestone overview is available in wiki.
Info | ||
---|---|---|
| ||
|
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Product Management | Are committed Product Backlog Stories been coded and marked as "Done" in Jira? | Y | Link to Jira | |
Are all tasks associated with committed Product Backlog Stories been marked as "Done" in Jira? | Y | Link to Jira | ||
Provide the project features list under the form of a bulleted list. | Please see the "new features" section of release notes | Link to evidence http://onap.readthedocs.io/en/latest/submodules/dcaegen2.git/docs/sections/release-notes.html | ||
Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off | None | |||
Release Management | Have all issues pertaining to FOSS been addressed? | Y | ||
Have all findings from previous milestones been addressed? | Y | Provide link to JIRA findings | ||
Development | Are all the Jenkins jobs successfully passed (verify + merge jobs)? | Y | ||
Are all binaries available in Nexus Release repository? | Y | Provide link to evidence https://nexus.onap.org/content/repositories/releases/org/onap/dcaegen2/ | ||
Are all Docker images available In Nexus? | Y | Provide link to evidence nexus3.onap.org:10002/onap/org.onap.dcaegen2.collectors.ves.vescollector:v1.1.0 nexus3.onap.org:10002/onap/org.onap.dcaegen2.deployments.bootstrap:v1.1.0 nexus3.onap.org:10002/onap/org.onap.dcaegen2.platform.cdapbroker:v4.0.0 nexus3.onap.org:10002/onap/org.onap.dcaegen2.platform.configbinding:v1.2.0 nexus3.onap.org:10002/onap/org.onap.dcaegen2.platform.deployment-handler:v1.1.0 nexus3.onap.org:10002/onap/org.onap.dcaegen2.platform.inventory-api:v1.2.0 nexus3.onap.org:10002/onap/org.onap.dcaegen2.platform.policy-handler:v1.1.0 nexus3.onap.org:10002/onap/org.onap.dcaegen2.platform.servicechange-handler:v1.0.0 | ||
Are the Java and Docker manifest updated with the same version as in Nexus Release repository? | Y | |||
Integration and Testing | Have all CSIT Use Cases (created by each project team) passed? | Y | Provide link to evidence https://jenkins.onap.org/view/dcagen2/job/dcaegen2-master-csit-testsuites/ https://jenkins.onap.org/view/dcagen2/job/dcaegen2-master-verify-csit-testsuites/ | Goal is to incease our confidence the latest commit did not break the major functionality. Jenkins CSIT Jobs |
Has the project code successfully passed the Daily Build process? | Y | Provide link to evidence | Goal is to ensure the latest project commit has not broken the Integration Daily Build | |
Has the project done the integration testing with related dependent projects? | Y | |||
Documentation | Has your team contributed and completed work in the following documentations in ReadTheDocs:
| Y | Provide Link to ReadTheDocs Release Notes http://onap.readthedocs.io/en/latest/submodules/dcaegen2.git/docs/sections/release-notes.html Provide Link to ReadTheDocs Project Documentation http://onap.readthedocs.io/en/latest/submodules/dcaegen2.git/docs/index.html |