Practice Area | Checkpoint | Yes/No | Evidences | How to? | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Product Management | Are all tasks associated with the release been marked as "Done" in Jira? | Y |
| |||||||||||||||||||||
Have all findings from previous milestones been addressed? | YReadthedocs placeholder was pending: https://onap.readthedocs.io/en/latest/templates/sections/logging.html | |||||||||||||||||||||||
Development | Have all Defects of priority Highest and High been in status "Done" in Jira? | Y |
Most of what's outstanding relates to documentation. | |||||||||||||||||||||
Are all JIRA issues used as a reference in a commit in status "Done" in Jira? | Y | Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful. | ||||||||||||||||||||||
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours. | YN | https://gerrit.onap.org/r/#/q/status:open+project:logging-analytics | ||||||||||||||||||||||
Are all the Jenkins jobs successfully passed (verify + merge jobs)? | N/A | Not applicable for R1. | ||||||||||||||||||||||
Has the team delivered all their release artifacts in Nexus Release or Nexus Staging repo? There should be at least ONE version of each artifacts available in Nexus Release or Nexus Staging repo. | N/A | Not applicable for R1. | Refer to Independent Versioning and Release Process for procedure | |||||||||||||||||||||
Integration and Testing | Have all CSIT Use Cases (created by each project team) passed? | N/A | Not applicable for R1. | |||||||||||||||||||||
Is there a Docker images image available for each repository? | N/A | The only new images for R1 are thirdparty third party – Elastic Stack. | ||||||||||||||||||||||
Has the project code successfully passed the Daily Build process? | N/A | Not applicable for R1. | Goal is to ensure the latest project commit has not broken the Integration Daily Build | |||||||||||||||||||||
Documentation | For RC0RC1, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template? | Y | Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed. Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK | |||||||||||||||||||||
For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team? | Y | None raised by documentation team as of 20171031 | ||||||||||||||||||||||
For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate? | ||||||||||||||||||||||||
For RC2, has the Documentation Team provided the final approval for your project documentation? |
Page Comparison
General
Content
Integrations