Beijing Pair-wise testing status: [In-progress] SB-07 environment

Image Added

Status update as of 31st May 2018 - 12:15 AM

SO - DMAAP - SDNC issues resolved. Fixes in APPC client library with SO working nicely. Tremendous team work !!!! Special thanks to Ruchira, Arthur, Brian, Marco, Elena, Kang, Dan, Jimmy, Rob, Randa, Ryan and Patrick.

Successfully tested the SO CM workflow end to end - pre-check, software upgrade and post-check went through successfully and the vGW instance was successfully upgraded.

Next to work with VID on request to SO (31st May morning!) - this is non-blocking for CM Beijing. VID provides a graphical user interface and the same workflow can also be invoked using SO (Which is tested successfully with vGW so far!)

Status update as of 30th May 2018 - 5:15 PM

...