Time
(mins)

Agenda Items

Presented By

Presos/Notes/Links/

 5 TSC Vice-Chair Election

 Congratulations to Lingli Deng , our re-elected TSC Vice-Chair !

75

Release Status

Projects: Frankfurt Milestone Status

  • Request clarifications about OJSI expectations for Frankfurt
    •  By M4, what it is expected by SECCOM?
      • Min. to be fixed: HTTP port + comments provided as part of M4 Release JIRA 
      • Fix what PTL can hanlde as part of Frankfurt otherwise will be plan for Guilin 

Action: Each impacted PTL to review current comments under 'All Security issues to be addressed" and start the discussions with Krzysztof Opasiak . If any concern then these will be handled during the next PTL call on 3/9/2020

Requirements: Frankfurt Release Requirements

  • Request exception for CMPv2 - req #140; req #76 to finalize code/debugging until RC0 agreed by impacted PTLs (Apps and Integration)
  • E2E L1 SM Modeling the optical Service
  • ActionSeshu Kumar Mudiganti , @Raghavan Subramanian to define the path to move forward not later than 3/12/2020
  • Vote to approve Release Manager recommendations for M4
  • Review Missing some M4 Scorecards

Integration Blockers: 1: Frankfurt Release Integration Test Blocking Issues

Integration Test Leads need to submit their test plan : 2: Frankfurt Release Integration Testing Status

Chaker Al-Hakim  Architecture Review Status

Risks: Frankfurt Risks

TSC Recommendations: NO GO

Resume Daily Highest/High defects status

AGREED #Requirements, Use Cases GREEN Approved by TSC

Action: David McBrideto kick-off vote offline for "Green" Projects (incl. projects that complete their action over th night) + Yellow Requirements/Use Cases


 30

POSTONED to 3/12

 El Alto Retrospective

Action Plan

 El Alto Retrospective Results (move to next week's meeting)

10

RelEng/Infrastructure

Remember - code coverage criteria i.e. 55% AND migration to SonarCloud must be completed by RC0 

15

 TSC Activities and Deadlines


 LF Networking Mentorship Program - 3/6/2020 EOD

TSC Task Force - Cloud Native 

  • Initial Feedback
  •  Request ONAP Subcommittees to identify 1 representative to join the ONAP CNF Task Force - Please send an e-mail to Kenny and David 

5

Upcoming Events

...

  •  format // for date,, @name for assigned to, action item, due //
  •  David McBride - add M4 Ticket discussion about "All security to be addressed" to the next PTL call on 3/9/2020
  •   Seshu Kumar Mudiganti , @Raghavan Subramanian to define the path to move forward not later than 3/12/2020
  •  David McBride to contact Owner of req #96
  •  Vimal Begwani to follow-up with Req #129, #38
  •  David McBride - work with PTLs to solve req #231 based on tickets created by Morgan Richomme
  •  Jessica Gonzalez  - send detailed email to PTLs regarding migration to Ubuntu 18
  •  David McBride to kick-off vote offline for "Green" Projects (incl. projects that complete their action over th night) + Yellow Requirements/Use Cases
  •  Morgan Richomme  to confirm that we can move to Ubuntu 18.04 in Frankfurt

...