S.No. | Topic | Description | Dependency | Tester | Status | Remarks | Progress update | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Service Design | Design of CST, and necessary templates for 1 type of service (e.g., eMBB): NST, NSST for RAN, RAN NF, Core & TN, Service Profile and Slice Profiles | COMPLETED | ||||||||||||||
2 | Design of necessary templates for 2nd type of service (e.g., mMTC): NST, NSST for RAN, RAN NF, Core & TN, Service Profile and Slice Profiles | Deepika S | DEFERRED | For mMTC, the performance requirements needs to be finalized, this will be deferred to next release. | |||||||||||||
3 | Service instantiation | See below table for (a) to (g) | Deepika S | IN PROGRESS COMPLETED | Assumption is manual intervention does not override ONAP selection | ||||||||||||
4 | Service instantiation with manual intervention | For scenario (c) in below table, operator shall override via NSMF portal in UUI the selection of reusable NSI and indicate creation of new NSI. | (c) for service instantiation should work first |
| |||||||||||||
5 | Service activation | Activate a service - this should result in activation of new NSI and associated new NSSIs. | (a) or (b) for service instantiation should work first. |
| |||||||||||||
6 | Activate a service - this should result in activation of S-NSSAI, and the activate command should pass to all the NSSMFs | (c) for service instantiation should work first |
| ||||||||||||||
7 | Service deactivation | Dectivate a service - this should result in deactivation of new NSI and associated new NSSIs. | Test case 5 should be completed |
| |||||||||||||
8 | Dectivate a service - this should result in deactivation of S-NSSAI, and the deactivate command should pass to all the NSSMFs | Test case 6 should be completed |
| ||||||||||||||
9 | Service termination | Terminate a service - this should terminate NSI and ALL associated NSSIs. Note: The proper configuration updates should be sent to the RAN NFs. | At least 1 service instantiation test case should be completed | IN PROGRESS |
| CN NSSMF - deallocateNSSI WF needs to be fixed | |||||||||||
10 | Terminate a service - this should terminate NSI but terminate only RAN NSSI and TN BH NSSI, and not Core NSSI (Assumption: RAN NSSI terminated => RAN NF NSSI terminated, TN FH and MH NSSIs terminated) Note: The proper configuration updates should be sent to the RAN and Core NFs, and to TN NSSMF (for FH and MH NSSIs, using deallocateNSSI API). | At least 1 service instantiation test case involving reuse should be completed | IN PROGRESS COMPLETED | This can happen when only 1 Service Profile is linked to NSI and 1 Slice Profile each is linked to RAN & TN BH NSSIs, but > 1 Slice Profile is linked to Core NSSI.CN NSSMF - deallocateNSSI WF needs to be fixed | |||||||||||||
Terminate a service - this should terminate NSI but terminate only Core NSSI and TN BH NSSI, and not RAN NSSI (Assumption: RAN NSSI not terminated => RAN NF NSSI not terminated, TN FH and MH NSSIs not terminated) Note: The proper configuration updates should be sent to the RAN NFs and TN NSSMF (for FH and MH NSSIs, using modifyNSSI API). | At least 1 service instantiation test case involving reuse should be completed | IN PROGRESS
| This can happen when only 1 Service Profile is linked to NSI and 1 Slice Profile each is linked to Core & TN BH NSSIs, but > 1 Slice Profile is linked to RAN NSSI. | CN NSSMF - deallocateNSSI WF needs to be fixed | |||||||||||||
12 | Terminate a service - this should terminate NSI but terminate only Core NSSI and TN BH NSSI, and not RAN NSSI (Assumption: RAN NSSI not terminated => RAN NF NSSI not terminated, TN FH and MH NSSIs not terminated) Note: The proper configuration updates should be sent to the RAN NFs, Core NFs and TN NSSMF (for FH and MH NSSIs, using modifyNSSI API). | At least 1 service instantiation test case involving reuse should be completed | IN PROGRESS
| This can happen when only 1 Service Profile is linked to NSI and > 1 Slice Profile each is linked to RAN, Core & TN BH NSSIs. | CN NSSMF - deallocateNSSI WF needs to be fixed | ||||||||||||
13 | KPI Computation | Operator should be able to view a KPI within a given time range (a KPI that is computed by KPI MS) via UUI | KPI Computation MS policies should be configured properly, DES termplates should be set up |
| |||||||||||||
14 | Closed Loop | Initiate PM data generation from RAN and show the Closed Loop action triggered by ONAP, and updates done in RAN (using RAN-Sim) | COMPLETED | ||||||||||||||
15 | Intelligent Slicing | Initiate PM data generation from RAN and show ML-based Closed Loop action triggered by ONAP, and updates done in RAN (using RAN-Sim) | Niranjana Y | COMPLETED |
Service Instantiation scenarios (test case 3 above)
...
S.No. | Priority | Input service | NSI | RAN NSSI | Core NSSI | TN BH NSSI | Tester | Status | Remarks |
---|---|---|---|---|---|---|---|---|---|
a | 1 | eMBB like service parameters No sharing | New | New | New | New | COMPLETED | ||
b | 1 | eMBB like service parameters Sharing allowed | New | New | New | New | COMPLETED | Pre-requisite: There is no existing shareable suitable NSI or NSSIs | |
c | 1 | eMBB like service parameters Sharing allowed | Reuse | X | X | X | COMPLETED | X = don't care as automatically all NSSIs are reused | |
d | 1 | eMBB or mMTC like service parameters Sharing allowed | New | Reuse | New | New | COMPLETED | Pre-requisite: There is an existing RAN NSSI that is suitable and can be reused. This requires either providing the service parameters in such a way RAN NSSI is reused, or creating a suitable and shareable RAN NSSI upfront. | |
e | 1 | eMBB or mMTC like service parameters Sharing allowed | New | New | Reuse | New | COMPLETED | Pre-requisite: There is an existing Core NSSI that is suitable and can be reused. This requires either providing the service parameters in such a way Core NSSI is reused, or creating a suitable and shareable Core NSSI upfront. | |
f | 2 | eMBB or mMTC like service parameters Sharing allowed | New | Reuse | Reuse | New | COMPLETED | Pre-requisite: There is an existing RAN & Core NSSI that is suitable and can be reused. This requires either providing the service parameters in such a way RAN & Core NSSI are reused, or creating suitable and shareable RAN & Core NSSIs. | |
g | 2 | eMBB or mMTC like service parameters. with coverageArea more than what is already supported in a suitable existing and shareable NSI Sharing allowed | New | New | New | New | DeferredDEFERRED | Pre-requisite: There should be a suitable existing NSI that is shareable, but whose coverageArea is smaller or does not have full overlap with the new service request. |
...
S.No. | Topic | Description | Dependency | Tester | Status | Remarks | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Service Design | Design of CST, and necessary templates for 1 type of service (e.g., eMBB): NST, NSST for RAN, RAN NF, Core & TN, Service Profile and Slice Profiles |
| |||||||||||
2 | Design of necessary templates for 2nd type of service (e.g., mMTC): NST, NSST for RAN, RAN NF, Core & TN, Service Profile and Slice Profiles |
title | NOT STARTED
| For mMTC, the performance requirements needs to be finalized, this will be deferred to next release. | ||||||||||