The following items are expected to be completed for the project to Pass Release Sign-Off Milestone.
Release Sign-Off Milestone overview is available in wiki.
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Product Management | Are committed Product Backlog Stories been coded and marked as "Closed" in Jira? | Yes |
completed (52)
Not completed (0)
| ||||||||||||||||||||||
Are all tasks associated with committed Product Backlog Stories been marked as "Closed" in Jira? | Yes | Link to Jira | ||||||||||||||||||||
Provide the project features list under the form of a bulleted list. |
New services - SNMP |
Trap Collector, HV-VES, DataFileCollector |
, PNF Registration Handler DCAE Platform upgrades
|
Also specified under first section of the release notes: https://onap.readthedocs.io/en/casablanca/submodules/dcaegen2.git/docs/sections/release-notes.html | ||||
Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off | Yes | VES-Mapper, Heartbeat, TCA-Gen2 and PM-Mapper were identified as Stretch goal for R3. They provide additional value to DCAE: supporting data format mapping (to VES), detection of missing heartbeat messages from xNFs, replaced to CDAP TCA and translation of 3gpp bulk file into measurement. These functions were not identified for ONAP R3 usecases and was listed as stretch goals due to resource and time constraints. Except PM-Mapper, the other components have all delivered their docker container images, however the platform integration work and release compliance (sonar, csit, clm) work couldn't be addressed in time for Casablanca. The work on these would continue and targeted for Dublin. | ||
Release Management | Have all issues pertaining to FOSS been addressed? | |||
Have all findings from previous milestones been addressed? | Yes | Provide link to JIRA findings | ||
Development | Are all the Jenkins jobs successfully passed (verify + merge jobs)? | Yes | https://jenkins.onap.org/view/dcaegen2/ | |
Are all binaries available in Nexus Release repository? | Yes |
Are all Docker images available In Nexus? | Yes | Provide link to evidence | |
Are the Java and Docker manifest updated with the same version as in Nexus Release repository? | Yes | ||
Integration and Testing | Have all CSIT Use Cases (created by each project team) passed? | No | HV-VES |
CSIT jobs failin; pending merge https://gerrit.onap.org/r/#/c/73226/1 | Goal is to incease our confidence the latest commit did not break the major functionality. Jenkins CSIT Jobs |
Has the project code successfully passed the Daily Build process? | Yes |
https://jenkins.onap.org/view/dcaegen2/ | Goal is to ensure the latest project commit has not broken the Integration Daily Build | |||
Has the project done the integration testing with related dependent projects? | Yes | Casablanca Release Integration Testing Status | ||
Documentation | Has your team contributed and completed work in the following documentations in ReadTheDocs:
| Yes | https://onap.readthedocs.io/en/casablanca/submodules/dcaegen2.git/docs/sections/release-notes.html https://onap.readthedocs.io/en/casablanca/submodules/dcaegen2.git/docs/index.html | Provide Link to ReadTheDocs Release Notes Provide Link to ReadTheDocs Project Documentation |