DRAFT PROPOSAL FOR COMMENTS

This checklist is expected to be completed for the project to pass the M1 Release Planning Milestone.

filling out today 17 Jan

M1 Release Planning Milestone definition

  • Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
  • Fill out the Yes/No column
  • Provide link to evidence (when necessary)
    Info
    titleUsage



    Practice AreaCheckpointYes/NoEvidence - CommentHow to?
    Product ManagementAre Product Backlog Epics entered in Jira?Yes

    Jira Legacy
    serverSystem Jira
    jqlQueryproject=holmes LOG and issuetype=epic and fixVersion = "Beijing Release"
    counttrue
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

    Create a Backlog item

    Difference between a Product and Sprint Backlog

    Are Product Backlog Stories entered in Jira?Yes

    Jira Legacy
    serverSystem Jira
    jqlQueryproject=holmes LOG and issuetype=story and fixVersion = "Beijing Release"
    counttrue
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

    Create a Backlog item
    Are Product Backlog Stories linked to Product Backlog Epics?
    Product BacklogWork in a Sprint
    Are Product Backlog Stories prioritized?
    yesPrioritize a Backlog item
    Is the project team ready to estimate the top Stories (for coming Sprint) in Product backlog?
    yesEstimate a Backlog item
    Is the project team ready to create a 2 weeks Sprint in Jira?
    yesCreate a Sprint
    Are Team Members willing to create Tasks and associate them with Stories in Jira?
    yesCreate a Backlog item
    Has the project team plan to contribute to Platform Maturity Improvement?
    Provide a link to project Planning, Platform Maturity table.
    Release ManagementIs there a Release Planning Template available and completed in wiki?
    Release Planning Template
    Have all the "Release Components Name" been defined in Resources and Repositories (Deprecated) for your project? (this includes all Sub-Components Names, Sub-Components Repositories Names, Maven Group ID, Sub-Components Description)
    Resources and Repositories (Deprecated)
    Have all the "Resources committed to the Release" been defined in Resources and Repositories for your project? This includes First and Last names, LFID, Email Address and Location for PTL, Project Manager, Committers and Contributors.
    Resources and Repositories (Deprecated)
    Have new developers made themself familiar on the Onboarding Process?
    Yes

    Onboarding

    Described process on several LOG meetings to upcoming committers

    LOG Meeting Minutes 2018-01-02

    LOG Meeting Minutes 2017-12-19

    LOG Meeting Minutes 2017-12-05

    Is the project team aware of the Release milestone? Any misses will required TSC exception.
    YesLOG Meeting Minutes 2018-01-16
    Integration and TestingHas the Integration Team defined the vendor equipment list?
    Link to evidence

    Testing on Auto Continuous Deployment via Jenkins and Kibana

    discussed with Integration team on 20180116 and a couple meetings before

    Has the Integration Team defined the End 2 End Release Test Case?
    Link to evidenceTesting on Auto Continuous Deployment via Jenkins and Kibana
    Development



    Is the Project Team committed to develop Unit Test?


    Yesfor new code in https://gerrit.onap.org/r/#/c/28129/
    Has the Project Team put in place an Automated Unit Test infrastructure?
    Yes

    Jira Legacy
    serverSystem Jira
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyLOG-118

    Is the Project Team committed to create Continuous System Integration Testing (CSIT) test case?
    yes

    migrate Auto Continuous Deployment via Jenkins and Kibana and

    Jira Legacy
    serverSystem Jira
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyLOG-118

    Is the Project Team committed to perform Scrum ceremonies?
    yesScrum Overview (each meeting we review spring, epics and backlog)
    Are the Project Team members aware of Continuous Integration Principles (don't break the build, Fix the build,...)?
    YES

    Continuous Integration

    see Auto Continuous Deployment via Jenkins and Kibana

    Has the Project Team a clear understanding on the Code Coverage expectations?
    yes

    Code Coverage and Static Code Analysis

    Does the Project Team understand the Free and Open Source Software (FOSS) process?
    yes

    Free and Open Source Software

    We use the ELK stack, Kubernetes, Rancher, Filebeat, Jenkins

    Is the Project Team willing to fill out accordingly the FOSS table?
    yes

    Fill out sub-pages for each project under Free and Open Source Software

    Already filled

    Is the Project Team willing to comply to the Commit Process?
    yesCommit Messages - pushing the format and process, editing the page with devops adjustments,
    Does the Project Team understand the purpose of Code Review?
    yesCode Review - also added to the wiki
    Is the Project Team aware of the Coding Guidelines?
    yes

    Development Practices (Jave Coding Style)

    yes, added to the process