This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)
RC Release Candidate Milestone overview is available in wiki.
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Product Management | Are all tasks associated with the release been marked as "Done" in Jira? |
No - In Progress |
| |||||||||||||||||||||
Have all findings from previous milestones been addressed? |
Yes | ||
Development | Have all Defects of priority Highest and High been in status "Done" in Jira? |
Yes |
| ||||||||||||||||||||||
Are all JIRA issues used as a reference in a commit in status "Done" in Jira? | Yes | Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful. | |||||||||||||||||||||
Is there any pending commit |
related to Highest and High priority issues older than |
36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours. | No | https://gerrit.onap.org/r/#/q/status:open+projects:policy | |
Are all the Jenkins jobs successfully passed (verify + merge jobs)? |
Yes | https://jenkins.onap.org/view/policy/job/policy-common-master-verify-java/ https://jenkins.onap.org/view/policy/job/policy-common-master-merge-java/ https://jenkins.onap.org/view/policy/job/policy-drools-applications-master-verify-java/ https://jenkins.onap.org/view/policy/job/policy-drools-applications-master-merge-java/ https://jenkins.onap.org/view/policy/job/policy-engine-master-verify-java/ https://jenkins.onap.org/view/policy/job/policy-engine-master-merge-java/ https://jenkins.onap.org/view/policy/job/policy-drools-pdp-master-verify-java/ https://jenkins.onap.org/view/policy/job/policy-drools-pdp-master-merge-java/ | ||
Has the team delivered all their release artifacts in Nexus Releases repo? There should be at least ONE version of each artifacts available in Nexus Releases repo. | Yes | Staging artifacts were available. | Refer to Independent Versioning and Release Process for procedure |
Integration and Testing | Have all CSIT Use Cases (created by each project team) passed? |
Yes | https://jenkins.onap.org/view/policy/job/policy-master-csit-health/ | |
Is there a Docker images available for each repository? |
Yes | Docker staging images were available. | ||
Has the project code successfully passed the Daily Build process? | Yes | Goal is to ensure the latest project commit has not broken the Integration Daily Build | |
Documentation | For RC0, for project delivering binaries, has the team populated and validated all the sections |
of either the Platform Component or SDK template? | Yes | There are only a subset of the suggested Platform Component list that are applicable to policy: http://onap.readthedocs.io/en/latest/submodules/policy/engine.git/docs/index.html | Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed. Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK |
For RC1, has the team addressed |
any issue (recorded in JIRA) provided by the Documentation team? | n/a | ||
For RC2, |
n/a |