zoom bridge: https://zoom.us/j/283628617

Duration 60 minutes

Testing
DurationAgenda ItemRequested byNotes / Links
START RECORDING

Emergency Maintenance Release - Tag: 3.0.2

  • Final list of projects
    • Known participants: A&AI, DMaaP, CLAMP, VID, Policy, Portal
    • Possible security patches (Non certif) from: SDNC (python lib), APPC, CCSDK
    • Integration needs 5 working days to complete the sanity and verify use cases.
    • Readthedocs

    Jira Legacy
    serverSystem Jira
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyTSC-120

    CLAMP is OK, already tested by Integration - GO to deliver

    Need to define a timeline (question)


    M4 Preparation

    • Integration Blockers
    • Risks
    • Projects
    • Requirements
    • oParent Integration
    • Containers Procedure from
    Inegration
    • Integration/OOM Teams


    Please update M4 checklist by April

    3rd

    10th, 2019 noon - thank you

    Former user (Deleted)

    New Risk (MultiCloud): Seccom, S3P - request support from the community to provide additional resources


    CII Badging Grant/Right Access to be allocated to two people i.e. https://bestpractices.coreinfrastructure.org/en/projects/1718

    Actions (Catherine/Jim):

    #1 Ask PTLs to ensure they have enough access

    Then #2 Ask David Wheeler to provide additional access

    OOM/Integration to provide the procedure asap

    Request from Rich about Storage/Persistent Data Architecture Plan/PTLs - Single NFS server?