Test NO:TEST-10
Project:PNF
Sub-project:PNF Registration And Activation
Objective:Register And Activation of SEBA Pod to ONAP
Pre-conditions:
  1. SEBA Pod must be configured and be aware of its CorrelationId(PnfId)
  2. SEBA Pod must be aware of ONAP IP Address
  3. SEBA service must be instantiated.

Test Steps:

  1. The operator sends a rest request which contains SEBAs CorrelationId and ONAPs IP Address

Test Result:

  1. SEBA enters an active state in AAI.

Observation:

  1. SEBA Pod should be aware of OSAM GW and needs to connect.


10 Service LCM

10.1 OSAM Core Auto Scaling

...

Test Steps:

...

Test Result:

11 Data Storage

1110.1 Alarm Collection(Check the Use case tracking flow...)

Test NO:TEST-12
Project:DCAE
Sub-project:Data Collection
Objective:Use DCAE for storing alarms
Pre-conditions:
  1. SEBA service must be instantiated
  2. SEBA pod must be registered to ONAP
  3. OSAM GW must be matched with SEBA pod

Test Steps:

  1. Instantiate OSAM GW service.
  2. Instantiate SEBA service.
  3. Trigger SEBA pod to register DCAE
  4. Plug OLT to SEBA pod

Test Result:

  1. SEBA should send an event through OSAM GW to DCAE.

Observation:

  1. OSAM UI should receive an event that OLT is plugged